Bagalkot-Kudachi railway line to be completed by the end of 2025

Senior MLA Basavaraja Rayareddy urges Minister to give priority to complete railway work between Gadag and Wadi

September 06, 2023 10:39 pm | Updated September 07, 2023 11:47 am IST - Bengaluru

The estimated cost of the 142-km Bagalkot-Kudachi railway line would be ₹1,530 crore. Of the 2,496 acres required for the line, 2,476 acres have been acquired so far.

The estimated cost of the 142-km Bagalkot-Kudachi railway line would be ₹1,530 crore. Of the 2,496 acres required for the line, 2,476 acres have been acquired so far. | Photo Credit: Photo for representation only

The State government has set a deadline of completing Bagalkot-Kudachi railway line by the end of 2025 and Gadag-Wadi line by March 2026. Both railway lines provide connectivity to various towns in north Karnataka.

The Karnataka government and Indian Railways would equally share the cost of both projects. The estimated cost of the 142-km Bagalkot-Kudachi railway line would be ₹1,530 crore. Of the required land of 2,496 acres, 2,476 acres have been acquired so far.

Minister for Infrastructure Development M.B. Patil, who reviewed progress of both projects with senior officials of the government on Wednesday, said the railway line between Bagalkot-Kachidoni-Lokapura (60 km) would be completed by March 2024 and then the movement of trains would be commenced. The tender process has been completed for taking up works from Kudachi side and work between Kudachi and Jagadal would start soon, he said.

The cost of Gadag-Wadi project is estimated at ₹1922 crore. A total of 4,002 acres would be required for the project and 3,945 acres had been acquired so far.

Referring to the existence of railway line between Gadag and Talakal, he said laying of the line between Talakal and Kustagi would be completed by March 2024 and then movement of trains would begin on an experimental basis. Work between Wadi and Shorapura was under progress, he said.

Senior MLA Basavaraja Rayareddy has urged the Minister to give priority to complete the railway work between Gadag and Wadi. The Minister instructed officials to inspect the work regularly to ensure quality of works.

Koppal MP Karadi Sanganna, and Lingasugur MLA Manappa Vajjal were present on the occasion.

0 / 0
Sign in to unlock member-only benefits!
  • Access 10 free stories every month
  • Save stories to read later
  • Access to comment on every story
  • Sign-up/manage your newsletter subscriptions with a single click
  • Get notified by email for early access to discounts & offers on our products
Sign in

Comments

Comments have to be in English, and in full sentences. They cannot be abusive or personal. Please abide by our community guidelines for posting your comments.

We have migrated to a new commenting platform. If you are already a registered user of The Hindu and logged in, you may continue to engage with our articles. If you do not have an account please register and login to post comments. Users can access their older comments by logging into their accounts on Vuukle.