Roadworks in central areas of Chennai in full swing to meet deadline of September 30

Of the 1,389 interior roads that need to be laid, only 361 have been completed so far; In the past two months, nearly 40 km of road laid across bus routes and interior parts of the central region of Chennai

Published - July 18, 2023 09:39 pm IST - CHENNAI

Twenty contractors have been roped in for the construction of drains and they have been told to meet the deadline.

Twenty contractors have been roped in for the construction of drains and they have been told to meet the deadline. | Photo Credit: B. JOTHI RAMALINGAM

Since May 1 this year, the Greater Chennai Corporation has laid a total of 1,093 roads out of 3,767 tendered, including 897 bituminous and 193 concrete roads, across the city running to a length of 193 km. These include both bus route roads and interior roads.

Despite hurdles posed by the Chennai Metropolitan Water Supply and Sewerage Board’s work in re-laying some utility lines, the civic body is working quickly to complete most of the work before the onset of monsoon. “One cannot use the situation in Madipakkam and Manapakkam as a reflection of the entire city because in many places, work has been completed,” says a senior official. 

Of the 1,389 interior roads that need to be laid in central city, work on only 361 roads have been completed so far with a deadline of September 30 for the remaining 1,028 roads. According to Regional Deputy Commissioner Sheikh Abdul Rahman, this was because funds had been released in a staggered manner. In the past two months, nearly 40 km of road, including bus routes and interiro lanes, had been laid in the region.

Nearly 18 km of work on storm-water drains is in progress along 44 roads and officials have been strictly instructed to complete them by September 15. “Work along short but vital stretches is on but began only a couple of weeks ago,” said Mr. Rahman.

Twenty contractors have been roped in for the construction of drains, but the pace of work varies depending on the conditions. An official said the work was at a slower than the desired pace but pressure was kept on the contractors through inspections to ensure that they meet the deadline. Plugging of illegal sewage connections was under way.

Some roads where the work is on include Perambur Barracks Road, Ambedkar College Road and New Farrance Road, 6th and 9th Avenue of Ashok Nagar and Ayanavaram Road. “Despite 9th Avenue not seeing any inundation during monsoon in the past, we have planned the drain from the disposal point to help the situation on 4th, 6th and 3rd Avenue,” said Mr. Rahman.

0 / 0
Sign in to unlock member-only benefits!
  • Access 10 free stories every month
  • Save stories to read later
  • Access to comment on every story
  • Sign-up/manage your newsletter subscriptions with a single click
  • Get notified by email for early access to discounts & offers on our products
Sign in

Comments

Comments have to be in English, and in full sentences. They cannot be abusive or personal. Please abide by our community guidelines for posting your comments.

We have migrated to a new commenting platform. If you are already a registered user of The Hindu and logged in, you may continue to engage with our articles. If you do not have an account please register and login to post comments. Users can access their older comments by logging into their accounts on Vuukle.