• Indian Space Research Organisation (ISRO) successfully carried out two more hot tests on the Gaganyaan Service Module Propulsion System (SMPS) at ISRO Propulsion Complex (IPRC), Mahendragiri, on July 26.
  • These tests marked the second and third hot tests in the Service Module – System Demonstration Model (SM-SDM) Phase 2 test series. The first hot test was conducted on July 19. During the July 26 tests, the thrusters were operated in both continuous and pulse mode, in sync with the mission profile.
  • Three more hot tests are scheduled to demonstrate de-boosting requirements and off-nominal mission scenarios. These tests will further validate and refine the performance of the propulsion system, ensuring its readiness for the upcoming Gaganyaan mission.