Stalemate over GST, royalty waiver for Kundannur-Angamaly bypass continues

A GO on the waiver is crucial to issuing the 3(A) notification to kick-start the process to acquire 287 hectares for the semi-access controlled NH corridor

March 07, 2024 01:14 am | Updated 01:14 am IST - KOCHI

The National Highways Authority of India (NHAI) is in a fix as a government order (GO) waiving Goods and Services Tax (GST) and royalty for constructing the 44-km Kundannoor-Angamaly NH 544 Bypass (Kochi Bypass) is yet to be issued, despite the government granting in-principle clearance for the waiver in January, informed sources said.

The greenfield NH project holds the key to decongesting both the Aroor-Edappally bypass and the Edappally-Angamaly NH 544 corridor — two of the most congested NH stretches in the State. A GO on the waiver is crucial to issuing the 3(A) notification to kick-start the process to acquire 287 hectares for the semi-access controlled NH corridor.

“The uncertainty over the waiver is taking a heavy toll, considering that the detailed project report [DPR] consultant of the NH project has been idling for the past several months. This in turn has led to the National Highways Authority of India [NHAI] incurring undue ‘establishment expenses’, while fear is rife that the total project cost would exceed the estimated ₹6,000 crore owing to the rise in land value and prices of raw materials. The worst part is that the stalemate continues even after the Chief Minister directed the Finance and other departments in January to take steps to complete the widening of NH 66 in a time-bound manner,” sources said.

The NHAI had in January ‘put on hold’ the Kochi Bypass project owing to the continuing uncertainty over the GO regarding the waiver. The Centre had insisted on the waiver after exempting the State from pooling in with 25% of the cost of land acquisition. The development of Kollam-Sengottai NH too is hanging fire due to delay on the part of the State government in issuing the GO.

Little has changed despite reminder letters, the sources added and expressed fear that the NHAI might now ‘back off’ from the two projects if the stalemate continued.

Sources in the government said a GO was awaited once the waiver was finally cleared by the Finance department. “There is no justification for the delay since there is no upfront payment that the government has to make,” they said.

Top News Today

Sign in to unlock member-only benefits!
  • Access 10 free stories every month
  • Save stories to read later
  • Access to comment on every story
  • Sign-up/manage your newsletter subscriptions with a single click
  • Get notified by email for early access to discounts & offers on our products
Sign in

Comments

Comments have to be in English, and in full sentences. They cannot be abusive or personal. Please abide by our community guidelines for posting your comments.

We have migrated to a new commenting platform. If you are already a registered user of The Hindu and logged in, you may continue to engage with our articles. If you do not have an account please register and login to post comments. Users can access their older comments by logging into their accounts on Vuukle.