Solar power producers move court against curbs on output

They were asked to cut back on generation by the State power utlity

Published - December 23, 2017 11:40 pm IST - CHENNAI

  Clean energy:  Non-evacuation of solar power at times of peak generation is resulting in wastage of installed infrastructure, say the companies.

Clean energy: Non-evacuation of solar power at times of peak generation is resulting in wastage of installed infrastructure, say the companies.

Adani Green Energy (Tamil Nadu) and a few other private solar power generators in the State have approached the Madras High Court, accusing the Tamil Nadu Generation and Distribution Corporation (Tangedco) and the Tamil Nadu State Load Despatch Centre (TNSLDC) of not allowing solar plants to generate power to their full capacity by issuing oral instructions to back down for about 7 to 10 hours every day.

Justice M. Duraiswamy has clubbed all their cases and posted them for hearing on January 10.

In its affidavit, Adani Green Energy (TN), which had set up a 216 MW solar power plant at Kamuthi taluk in Ramanathapuram district, said it had invested ₹1,477.61 crore in the project and was now facing bankruptcy because of the curbs imposed by the State entities in violation of their commitment to purchase power.

According to the company, the State government had notified its Solar Energy Policy in 2012 with a vision to generate 3,000 MW of solar power by 2015.

‘Heavy losses’

One of the aspects of the policy was to encourage setting up of solar power plants. Aspiring project developers came forward to set up plants and Tangedco promised to procure energy generated by them through a long-term power purchase agreement up to a capacity of 1,000 MW.

On September 12, 2014, the Tamil Nadu Electricity Regulatory Commission (TNERC) issued a comprehensive tariff order and fixed tariff for purchase of solar power at ₹7.01 a unit. Subsequently, the petitioner company entered into an energy purchase agreement with Tangedco for supplying 216 MW of power at the rate fixed by TNERC. One of the clauses of the agreement was that the power would be evacuated to the maximum extent.

“However, the petitioner has been continuously forced to suffer huge losses due to backing down instructions from the TNSLDC and forceful disconnection/curtailment of supply from their solar power plant by Tangedco/Tamil Nadu Transmission Corporation (Tantrasco).

“Invariably, these instructions are issued over the phone without any written confirmation either prior to or after backing down/disconnection in the name of real time operation,” the company alleged.

Contending that such curtailment could be done only in exceptional circumstances of maintaining grid stability or safety and that too as a last resort, including backing down of conventional generators, the company said: “Non-evacuation of solar power at times of peak generation... is a wastage of installed infrastructure... By such conduct, the respondents are breaching their obligation in so far as ‘Must Run’ status of the petitioner was concerned.”

0 / 0
Sign in to unlock member-only benefits!
  • Access 10 free stories every month
  • Save stories to read later
  • Access to comment on every story
  • Sign-up/manage your newsletter subscriptions with a single click
  • Get notified by email for early access to discounts & offers on our products
Sign in

Comments

Comments have to be in English, and in full sentences. They cannot be abusive or personal. Please abide by our community guidelines for posting your comments.

We have migrated to a new commenting platform. If you are already a registered user of The Hindu and logged in, you may continue to engage with our articles. If you do not have an account please register and login to post comments. Users can access their older comments by logging into their accounts on Vuukle.