At present, floodwaters from 1189 sq.km of the Chennai Metropolitan Area drain into the sea at Ennore through the Ennore Creek, near Napier Bridge through the Cooum river, near Foreshore Estate through the Adyar river, and at Kovalam creek.— Photo: K.V. Srinivasan

At present, floodwaters from 1189 sq.km of the Chennai Metropolitan Area drain into the sea at Ennore through the Ennore Creek, near Napier Bridge through the Cooum river, near Foreshore Estate through the Adyar river, and at Kovalam creek.— Photo: K.V. Srinivasan

There are efforts to revive an old proposal to create a fifth channel in Chennai to drain floodwater into the sea. Following a study of what could have minimised the damage from the recent floods, supervisory officers appointed by the State Government have suggested that the proposal to develop a new channel connecting Okkiyam Madavu to the Injambakkam be given a second chance.

At present, floodwaters from 1189 sq.km of the Chennai Metropolitan Area drain into the sea at Ennore through the Ennore Creek, near Napier Bridge through the Cooum river, near Foreshore Estate through the Adyar river, and at Kovalam creek.

According to one of the suggestions by the supervisory officers, having a fifth channel could be of immense help in draining floodwater during heavy rains.

According to these officers, the development of a new 30-metre wide waterway from Okkiyum Maduvu to the sea near Injambakkam could help drain more than 3000 cusec of floodwater during heavy floods.

This proposal was shelved due to the challenges of land acquisition from East Coast Road (ECR) to the sea. “Acquisition of more than 10,000 sq.m of private land from ECR to the sea was a challenge. While the construction of the waterway was estimated at Rs. 60 crore, land acquisition was estimated at Rs. 200 crore. So, a decision to shelve the project was taken,” said an official.

The officials had identified a strip of government land from Okkiyam Maduvu to ECR in Injambakkam for the project.

Fewer encroachments had been reported along the stretch.

After shelving the project, a decision to widen the Buckingham Canal from 30 metres near Okkium maduvu to 100 metres was made. This move was aimed at flood management.

The 100-metre-wide waterway was designed to drain floodwaters from most neighbourhoods of Rajiv Gandhi Salai and East Coast Road through Muttukadu. But the design proved a failure during the recent floods, prompting a review of the existing infrastructure.

Geometry of waterways

Following the floods, civic officials at the local level started collecting data on geometry of waterways, flow conditions of drains, catchment area characteristics, land use plan, catchment plans, obstructions to flow, cross-drainage structure and public utilities near the drains.

The design of the fifth channel could also be made along a 1.3-metre-long strip of land without affecting the operations of amusement parks in the area.

“A proposal to offer boating services in the channel is also likely to promote tourism. Floodwaters will also recede easily,” said an official.

0 / 0
Sign in to unlock member-only benefits!
  • Access 10 free stories every month
  • Save stories to read later
  • Access to comment on every story
  • Sign-up/manage your newsletter subscriptions with a single click
  • Get notified by email for early access to discounts & offers on our products
Sign in

Comments

Comments have to be in English, and in full sentences. They cannot be abusive or personal. Please abide by our community guidelines for posting your comments.

We have migrated to a new commenting platform. If you are already a registered user of The Hindu and logged in, you may continue to engage with our articles. If you do not have an account please register and login to post comments. Users can access their older comments by logging into their accounts on Vuukle.