Hassan-Bengaluru line misses another deadline

South Western Railway hopeful of commissioning the new line by December

Updated - March 31, 2016 07:18 am IST

Published - March 31, 2016 12:00 am IST - MANGALURU:

The South Western Railway (SWR) will miss the March 2016 deadline given by the then Minister for Railways D.V. Sadananda Gowda to complete the Bengaluru-Hassan new railway line. The construction wing of South Western Railway has now stumbled upon a bottleneck, which can be termed the final one, in the form of non-availability of 14 acres of land to lay 4 km line between Solur and Tippasandra in Ramanagaram district.

Several hurdles in the past, including the Kunigal Stud Farm issue and construction of bridges on National Highways, had delayed the project. Otherwise, the new line is almost ready, highly placed sources in the South Western Railway told The Hindu .

Instead of the district administration, Karnataka Industrial Area Development Board (KIADB) is proceeding with the acquisition of 14 acres of land and South Western Railway is hopeful of a resolution in a month. On getting land, the line should physically be ready by June, the sources said.

However, South Western Railway would take more time to make the track operational as additional infrastructure has to be created.

Works on signalling, telecommunication, station facilities, could take about another five months and the line is likely to be commissioned by December this year, the sources said.

Parts of the new line have been commissioned and regular train service is run between Bengaluru and Nelamangala. The Hassan line branches out of the Bengaluru-Tumakuru line at Chikkabanavara towards Nelamangala. Similarly, a passenger train runs on the section between Hassan and Shravanabelagola, which was commissioned in 2006 during the Mahamastakabhisheka of Bahubali.

T.P. Lokesh, a Bengaluru resident, cast doubts on South Western Railway’s claims. He told The Hindu that tenders for signalling were called for recently and it would take time to finalise them.

South Western Railway hopeful of commissioning the new line by December

0 / 0
Sign in to unlock member-only benefits!
  • Access 10 free stories every month
  • Save stories to read later
  • Access to comment on every story
  • Sign-up/manage your newsletter subscriptions with a single click
  • Get notified by email for early access to discounts & offers on our products
Sign in

Comments

Comments have to be in English, and in full sentences. They cannot be abusive or personal. Please abide by our community guidelines for posting your comments.

We have migrated to a new commenting platform. If you are already a registered user of The Hindu and logged in, you may continue to engage with our articles. If you do not have an account please register and login to post comments. Users can access their older comments by logging into their accounts on Vuukle.