Signature Bridge still hanging fire after 13 years

Announced in 2004, it received Delhi Cabinet's nod in 2007

Updated - March 27, 2017 10:11 am IST

Published - March 27, 2017 10:06 am IST - NEW DELHI

A BRIDGE TOO FAR: A view of the under-construction Signature Bridge near Wazirabad in Delhi.

A BRIDGE TOO FAR: A view of the under-construction Signature Bridge near Wazirabad in Delhi.

It has been under construction for a decade but the Signature Bridge in Wazirabad, an ambitious Delhi government project that seeks to connect the northern and eastern extremities of the Capital, is yet to see the light of day.

In fact, the almost ₹1,600-crore project — with its steel towers planned to be double the height of Qutub Minar and proposed waterfront development, which successive governments including the AAP intend to build into a tourist attraction — is expected to miss its sixth construction deadline in the coming months.

According to the government, the Signature Bridge had obtained environmental clearance in 2011 and was set to be completed by December 2013. The date of completion was pushed to June 2016 and then July 2017. However, sources said the project will be completed by December 2017.

Modified estimate

According to sources, the bridge was proposed for the first time as early as 1997, with initial cost pegged at ₹464 crore. Announced in 2004, the project received a nod from the Delhi Cabinet in 2007 and was initially expected to be completed at a modified estimate of ₹1,131 crore by the Commonwealth Games which were held in the Capital in October 2010.

Over the years, the initial cost of the project rose to ₹1,594 crore (in 2015) which, according to sources, is a significant reason behind the government’s decision not to scrap it.

Asymmetrical design

The main bridge, according to government records, is 675-metre-long, asymmetrical and cable-stayed with two approaches. The eastern approach is 1.8-km-long and connects the main bridge with Marginal Bund Road at Khajuri Khas intersection.

LED lights

It also has a flyover and a ground-level rotary at Khajuri Khas intersection. The western approach has a flyover on Outer Ring Road, which covers the existing intersections at Timarpur, Nehru Vihar and Wazirabad.

Designed with a bow-shaped steel pylon, the longest slab without support on the project is expected to be 251-metre-long with LED lights. The new bridge will be 600-metre downstream the existing bridge and connect Outer Ring Road on the western bank with Wazirabad Road on the eastern bank of the Yamuna.

In January last year, Public Works Department (PWD) Minister Satyendar Jain had said the project will finally become operational by early 2017. According to Mr. Jain, while most of the work on the approach roads and loops leading to the bridge was at an advanced stage, the piling work for the bridge over the Yamuna was proving to be a problem.

'Technical issues'

Apart from connecting north-east part of the Capital to outer Delhi, the bridge will be a gateway to the Tronica City in adjacent Ghaziabad, which is being developed on the lines of sub-cities like Indirapuram and Kaushambi.

A senior government official said “a little less than half” the work on the project is pending even as factors ranging from an increase in the base prices of construction material and other “technical issues” had led to the increased cost.

The redesigning of the foundation of the bridge too was cited as a significant reason behind its delayed construction, which the government said it was confident of tiding over “at the earliest”.

0 / 0
Sign in to unlock member-only benefits!
  • Access 10 free stories every month
  • Save stories to read later
  • Access to comment on every story
  • Sign-up/manage your newsletter subscriptions with a single click
  • Get notified by email for early access to discounts & offers on our products
Sign in

Comments

Comments have to be in English, and in full sentences. They cannot be abusive or personal. Please abide by our community guidelines for posting your comments.

We have migrated to a new commenting platform. If you are already a registered user of The Hindu and logged in, you may continue to engage with our articles. If you do not have an account please register and login to post comments. Users can access their older comments by logging into their accounts on Vuukle.