TNERC not for lifting R & C measures entirely

Corporation told to revisit load-shedding pattern

March 23, 2012 09:16 am | Updated 09:16 am IST - CHENNAI

The Tamil Nadu Electricity Regulatory Commission (TNERC) has disagreed with the Tamil Nadu Generation and Distribution Corporation (TANGEDCO)'s proposal to lift the restriction and control (R and C) measures by June-end.

In its order passed on Thursday, the Commission directed the Corporation to relax the R and C measures in a graded manner by linking it to capacity addition.

In its order passed on Thursday, the TNERC, taking into consideration the demand-supply gap and the financial situation of the Corporation and the delay in commissioning of additional capacities, said: “As some generating units are getting commissioned, albeit with certain delays, the Commission is not inclined to lift the entire R and C measures by June-end 2012, as proposed by TANGEDCO in their petition.”

Considering the commencement of wind season from May, banking of wind energy and allowing Open Access Regulations to industrial consumers, the Commission was of the view that the shortage of power was expected to recede only after October/November this year.

The Commission pointed out that an order for lifting R and C totally by end of June 2012 would only create chaos in the distribution of electricity in the State. In a situation where the shortage was between 2,000 megawatt (MW) and 4,000 MW, it spelled out a road map for the scheduled and complete lifting of the R and C measures, based on the proposed capacity addition of 1,600 MW.

As per the R and C measures, 40 per cent reduction in demand during normal hours and 90 per cent reduction in demand during peak hours were being implemented on high tension industrial units. Also, scheduled load shedding was being implemented throughout the State for all consumers for a period of two hours in the city and four hours in all other parts of the State. For every 400 MW capacity addition, the high tension consumers would get a relief of 10 per cent during normal and evening peak hours.

The Commission also wanted the Corporation to revisit the load-shedding pattern in the entire State and make it more equitable.

0 / 0
Sign in to unlock member-only benefits!
  • Access 10 free stories every month
  • Save stories to read later
  • Access to comment on every story
  • Sign-up/manage your newsletter subscriptions with a single click
  • Get notified by email for early access to discounts & offers on our products
Sign in

Comments

Comments have to be in English, and in full sentences. They cannot be abusive or personal. Please abide by our community guidelines for posting your comments.

We have migrated to a new commenting platform. If you are already a registered user of The Hindu and logged in, you may continue to engage with our articles. If you do not have an account please register and login to post comments. Users can access their older comments by logging into their accounts on Vuukle.