NGT stays green nod for NTPC’s Karimnagar plant

Environmental Clearance put on hold for seven months, bench calls for fresh appraisal.

May 28, 2021 08:44 pm | Updated 08:46 pm IST - CHENNAI

The NTPC Super Thermal Power project at Ramagundam in Karimnagar District of Andhra Pradesh

The NTPC Super Thermal Power project at Ramagundam in Karimnagar District of Andhra Pradesh

The southern bench of the National Green Tribunal has put in abeyance the Environment Clearance (EC) granted to the 2x800 MW thermal power plant of the National Thermal Power Corporation (NTPC) in Karimnagar district in Telangana for a period of seven months or till a re-appraisal is done and additional conditions are imposed by the Ministry of Environment Forest and Climate Change (MoEF & CC) .

The Bench, while refusing to set aside the EC in toto, ordered that the Clearance be set aside for a reasonable period of time directing the MoEF & CC to instruct the NTPC to conduct a fresh Environment Impact Assessment (EIA) study and then direct the Expert Appraisal Committee (EAC) to appraise the EIA.

The NGT also instructed the MoEF to impose necessary additional conditions as required, consider them and then issue necessary amendments to the EC issued on October 21, 2016, after the conditions are met.

The NGT directed NTPC to conduct a radio-activity and heavy metal test of coal including alternative coal which it proposes to use for the project and the probable impact of it on the environment and the mitigative measures to be taken to reduce such impact.

The bench also directed the company to conduct cumulative impact assessment of ambient air quality modelling for a radius of 15 kms from the project area, conduct a fresh study regarding the area for installation of Flue Gas Desulfurisation system, hydro-geological impact on account of the ash pond, its location and the mitigation measures to be taken to prevent possible pollution of water quality in the area.

A proper study on the disposal of wastewater and effluents by using Zero Liquid Discharge method should also be done, the bench said.

All these will have to be completed within a period of seven months, the NGT said.

0 / 0
Sign in to unlock member-only benefits!
  • Access 10 free stories every month
  • Save stories to read later
  • Access to comment on every story
  • Sign-up/manage your newsletter subscriptions with a single click
  • Get notified by email for early access to discounts & offers on our products
Sign in

Comments

Comments have to be in English, and in full sentences. They cannot be abusive or personal. Please abide by our community guidelines for posting your comments.

We have migrated to a new commenting platform. If you are already a registered user of The Hindu and logged in, you may continue to engage with our articles. If you do not have an account please register and login to post comments. Users can access their older comments by logging into their accounts on Vuukle.