Landslips cut off road to Sabarimala

Traffic on Plappally-Pampa stretch affected for past 23 days, PWD starts repair work on a warfooting

September 07, 2018 07:15 pm | Updated 11:17 pm IST - PATHANAMTHITTA

 Retaining wall construction under way at Mayiladumpara on the Plappally-Pampa stretch of the Sabarimala Road on Friday.

Retaining wall construction under way at Mayiladumpara on the Plappally-Pampa stretch of the Sabarimala Road on Friday.

Vehicular traffic between Plappally and Pampa has been badly affected for the past 23 days following landslips at three places along the Plappally-Pampa stretch on the main trunk road leading to Sabarimala.

The side of Sabarimala Road has caved in at Kambakathumvalavu, Planthodu, and Mayiladumpara, posing high risk to vehicles since August 15.

The police have blocked the road, permitting only light motor vehicles on official duty to Pampa from Plappally.

The Kerala State Road Transport Corporation (KSRTC) has stopped all its seven services on the route from August 15, putting much hardship to the tribespeople at Attathode and surrounding areas.

At Attathode

Madhu Swami, who runs a hotel at Attathode, told The Hindu that he had to travel 60 km extra to Erumely to bring rice, provisions, vegetables, and other articles on a daily basis and not to speak of the plight of the people at the Attathode tribal settlement.

Children at the Government Tribal School at Kisumom have been badly affected with the blocking of vehicular traffic on the road, said Madhu Swami, a tribesman.

Meanwhile, the Public Works Department had swung into action on the fourth day of the landslip, following personal intervention of Minister for Public Works G. Sudhakaran. He had directed the PWD authorities to take immediate steps to construct protection walls and repair the damaged portion of the Sabarimala road.

The PWD wing has launched the earth-clearing work from a depth of nearly 200 ft, using giant earth movers, two weeks ago.

However, the mazonry and concrete works, estimated at nearly ₹1 crore, have been delayed owing to shortage of building materials following a ban on granite quarrying and crushing in the district.

PWD sources said the department would construct a gabion retaining wall at one place where the earth had developed a lateral crack.

0 / 0
Sign in to unlock member-only benefits!
  • Access 10 free stories every month
  • Save stories to read later
  • Access to comment on every story
  • Sign-up/manage your newsletter subscriptions with a single click
  • Get notified by email for early access to discounts & offers on our products
Sign in

Comments

Comments have to be in English, and in full sentences. They cannot be abusive or personal. Please abide by our community guidelines for posting your comments.

We have migrated to a new commenting platform. If you are already a registered user of The Hindu and logged in, you may continue to engage with our articles. If you do not have an account please register and login to post comments. Users can access their older comments by logging into their accounts on Vuukle.