Bilaspur tunnel collapse: Two workers rescued after nine days

National Disaster Response Force continues search operations for the third worker.

September 21, 2015 06:13 pm | Updated March 28, 2016 06:43 pm IST - Shimla

This September 18, 2015 photo shows the collapsed under-construction tunnel of Kiratpur-Manali four-lane road project, at Tihra in Bilaspur district of Himachal Pradesh. A National Disaster Response Force rescued two trapped workers on Monday, nine days after the accident.

This September 18, 2015 photo shows the collapsed under-construction tunnel of Kiratpur-Manali four-lane road project, at Tihra in Bilaspur district of Himachal Pradesh. A National Disaster Response Force rescued two trapped workers on Monday, nine days after the accident.

Nine days after they got trapped in a partially collapsed under-construction tunnel near Bilaspur in Himachal Pradesh, two workers were on Monday rescued and brought out even as search operations continued for the third worker who is still suspected stuck under the debris.

The rescued workers have been identified as Mani Ram and Satish Tomar, NDRF Director-General O.P. Singh, who is monitoring the rescue operation from New Delhi, told PTI.

However, there has been no communication with the third employee, Hriday Ram.

“We have rescued two of the three workers who were trapped in the tunnel for over a week. Beginning this morning our teams have also begun a horizontal drilling operation to see through the debris and find the third worker whom we suspect is trapped somewhere there,” Mr. Singh said.

The DG added that while he was still in contact with the NDRF rescue teams, initial inputs suggested that the rescued men were weak but talking.

The miraculous rescue operation by the men of the National Disaster Response Force came a day after incessant rains lashed the accident spot and a snag developed in the heavy rig that was drilling through to rescue the trapped.

The >employees were trapped inside tunnel No. 4 of Kiratpur-Nerchowk four-lane project near Bilaspur in Himachal Pradesh when a portion of it collapsed on September 12, 2015.

Visuals emerging from the spot showed the rescuers flashing the victory sign and screaming in jubilation after the two were brought out from the narrow and dark tunnel.

The drilling of 1.2-metre tunnel to reach the trapped persons was almost complete and less than 1 metre of drilling was left when the heavy drilling rig developed a snag on Sunday night, warranting replacement of a part of it and suspension of operations.

The rescuers, earlier, had also established communication with two of the three trapped labourers through digital cameras and microphones after hours of digging.

A 45-member NDRF team, with three specially chosen men in the lead, have been working in the operation for days now.

Food and water had been supplied to the trapped workers through a 47-metre-long and 4-inch-diameter bore.

0 / 0
Sign in to unlock member-only benefits!
  • Access 10 free stories every month
  • Save stories to read later
  • Access to comment on every story
  • Sign-up/manage your newsletter subscriptions with a single click
  • Get notified by email for early access to discounts & offers on our products
Sign in

Comments

Comments have to be in English, and in full sentences. They cannot be abusive or personal. Please abide by our community guidelines for posting your comments.

We have migrated to a new commenting platform. If you are already a registered user of The Hindu and logged in, you may continue to engage with our articles. If you do not have an account please register and login to post comments. Users can access their older comments by logging into their accounts on Vuukle.