Central Vista project | Heritage panel clears Parliament project

The clearance was mandated by SC in its January 5 judgment allowing the project

January 11, 2021 05:31 pm | Updated 08:41 pm IST - New Delhi

In the majority verdict, the apex court said that prior permission shall be taken from heritage conservation committee and other relevant authorities before start of construction at new sites.

In the majority verdict, the apex court said that prior permission shall be taken from heritage conservation committee and other relevant authorities before start of construction at new sites.

The Union government’s proposal to construct a new Parliament building was on Monday approved by the Heritage Conservation Committee (HCC), whose clearance was mandated by the Supreme Court in its January 5 judgment allowing the project.

Also read: Govt. explains the need for a new Parliament building

The apex court ordered that the permission of the HCC, which is headed by a Housing and Urban Affairs (HUA) Ministry additional secretary and comprises government officials primarily, should be obtained before any work starts on the ground.

At a press conference, HUA Secretary Durga Shanker Mishra said the HCC had discussed the proposal and cleared it on Monday. The HCC looked at the preservation of heritage as per the Unified Building Bye-Laws, 2016. Permission was not sought earlier as the Ministry, whose Central Public Works Department is carrying out the project, felt there was no heritage involved. The new building was proposed to be built adjacent to the existing Parliament, which was built in the 1920s.

Since the court ordered it to get the approval of the HCC, the Ministry had complied, Mr. Mishra said. HUA Minister Hardeep Puri said the timeline for the completion was 2022, the 75th year of Independence.

Opinion | Beyond the veils of secrecy, the Central Vista project is both the cause and effect of its own multiple failures

Another part of the larger Central Vista Avenue redevelopment project, the revamp of Rajpath or Central Vista Avenue, would be started by February 1, with the contract likely to be awarded soon, Mr. Mishra said. The Republic Day Parade next year would be held on the revamped Rajpath.

The cost

Asked about the cost of the Central Vista redevelopment project, the Minister said: “I don’t know what the overall cost will be. The cost will be absorbed by each of the Ministries in their own Budget.”

The project includes the construction of a new Parliament building, redevelopment of Rajpath, development of a Central Secretariat for all Ministries, new Prime Minister’s residence and office and Vice-President’s residence.

Mr. Puri said the Ministry would be launching a website on public consultations regarding the project soon, in response to criticism that transparent processes have not been followed.

0 / 0
Sign in to unlock member-only benefits!
  • Access 10 free stories every month
  • Save stories to read later
  • Access to comment on every story
  • Sign-up/manage your newsletter subscriptions with a single click
  • Get notified by email for early access to discounts & offers on our products
Sign in

Comments

Comments have to be in English, and in full sentences. They cannot be abusive or personal. Please abide by our community guidelines for posting your comments.

We have migrated to a new commenting platform. If you are already a registered user of The Hindu and logged in, you may continue to engage with our articles. If you do not have an account please register and login to post comments. Users can access their older comments by logging into their accounts on Vuukle.