Vizag airport witnesses steady growth despite pandemic curbs

Officials put passenger traffic for June at 37,323

July 15, 2020 11:10 pm | Updated 11:10 pm IST - VISAKHAPATNAM

Visakhapatnam International Airport recorded 20,212 arrivals and 17,111 departures of flights in June.

Visakhapatnam International Airport recorded 20,212 arrivals and 17,111 departures of flights in June.

The Visakhapatnam International Airport has witnessed a slow but steady growth in the number of passengers during the last two and a half months, despite the restrictions imposed on operation of flights in the wake of COVID-19.

Even as the domestic flight services have been restored partially, international flights are yet to be resumed. However, the airport continues to receive passengers from different countries who arrived here by repatriation flights as part of the Vande Bharat Mission (VBM) and chartered flights.

The domestic flights were partially restored in May after the lockdown norms were relaxed and the airport handled 7,369 passengers during the month, with 3,934 arrivals and 3,435 departures. The corresponding figures for June are 20,212 arrivals and 17,111 departures, taking the total passenger count to 37,323.

During the lockdown period in April, the airport handled 24 domestic passengers through non-scheduled domestic flights, 48 domestic and 541 international passengers (non-scheduled) in May and 116 domestic and 2,594 international passengers (non-scheduled) in June this year. The frequency of domestic flights increased from 118 in May to 406 in June, while the non-scheduled movements included six domestic flights in April, 19 domestic and four international flights in May and, 41 domestic and 25 international non-scheduled flights.

The 27 repatriation flights handled by the airport between May 19 and July 6 brought 3,558 passengers to Vizag and 163 passengers left the city by return flights.

Meanwhile, the linear expansion works undertaken at the airport are nearing completion. “The erection of structures has been completed while the flooring works are in progress. Additional elevators have arrived, but they are yet to be installed. Once the civil works are completed, the elevators will be installed,” airport Director M. Raja Kishore told The Hindu .

The airport authorities have placed order for a conveyor belt and it is yet to arrive from abroad.

N 5 taxi track

“The N 5 taxi track work has been completed and the clearance has been obtained from the Navy. A team of the Bureau of Civil Aviation Security is expected to issue the final clearance for operation of the taxi track soon. It is being delayed due to the pandemic,” he added.

0 / 0
Sign in to unlock member-only benefits!
  • Access 10 free stories every month
  • Save stories to read later
  • Access to comment on every story
  • Sign-up/manage your newsletter subscriptions with a single click
  • Get notified by email for early access to discounts & offers on our products
Sign in

Comments

Comments have to be in English, and in full sentences. They cannot be abusive or personal. Please abide by our community guidelines for posting your comments.

We have migrated to a new commenting platform. If you are already a registered user of The Hindu and logged in, you may continue to engage with our articles. If you do not have an account please register and login to post comments. Users can access their older comments by logging into their accounts on Vuukle.