Full quantum of Tungabhadra water for Anantapur still a distant dream

Canal modernisation works make no headway

August 13, 2020 12:10 am | Updated 12:10 am IST - ANANTAPUR

Tungabhadra Dam’s High Level Main Canal where modernisation work has been completed.

Tungabhadra Dam’s High Level Main Canal where modernisation work has been completed.

Anantapur district getting the full complement of its share of water from the Inter-State irrigation project Tungabhadra Dam at Hospet might remain a distant dream with all the modernisation works that were taken up on the High-Level Main Canal (HLC) at an estimated cost of ₹470 crore in 2008 have been pre-closed by the State government.

Contractors of all the six packages in the HLC Stage -I had applied for pre-closure and work worth ₹148.6 crore has not been completed. In the HLC Stage-II project for modernisation of HLC’s branch canals, work on Yadiki Canal System is nearing completion with ₹22 crore and the balance remained due to land acquisition problems. Work on another three branch canals, valued at ₹350 crore, is in progress.

Modernisation works on the 105-km stretch of HLC in Karnataka portion have been completed bringing 4,000 cusecs up to the Andhra Pradesh border, but the A.P. portion of the canal is so weak that it cannot carry more than 1,800 to 2,000 cusecs with bunds breaching at several places and these incidents becoming a routine phenomenon now.

Tungabhadra’s HLC, which is supposed to bring 32 tmcft, yields only 21 tmcft due to the siltation of the dam and in the last 10 years, the district has been able to draw only between 10 tmcft and 15 tmcft. Last year, when the dam got filled to its brim at least thrice, Andhra Pradesh was not in a position to draw its quota of water.

In the current season, the inflows to TB Dam have been varying between 1 lakh cusecs and 1.5 lakh cusecs for the past one week and on Tuesday evening it was at 98,916 with reservoir storage being recorded as 80.17 tmcft.

Different packages

The modernisation works were tendered under different packages in 2008 from 105th KM to 189th KM of the HLC’s main canal, but the crucial structures that have to be modernised to allow full flow of water, have been left out and only canal lining and widening (earth work) has been done to some extent. The project was to be completed by 2012 without taking a crop holiday, but works worth ₹320 only progressed and the remaining portion remains unfinished.

If the State Finance Department completes the modernisation contracts closure process, only repair works can be taken up for the current and next season and unless there is a strong public / political pressure, the widening and modernisation works might end at this stage.

0 / 0
Sign in to unlock member-only benefits!
  • Access 10 free stories every month
  • Save stories to read later
  • Access to comment on every story
  • Sign-up/manage your newsletter subscriptions with a single click
  • Get notified by email for early access to discounts & offers on our products
Sign in

Comments

Comments have to be in English, and in full sentences. They cannot be abusive or personal. Please abide by our community guidelines for posting your comments.

We have migrated to a new commenting platform. If you are already a registered user of The Hindu and logged in, you may continue to engage with our articles. If you do not have an account please register and login to post comments. Users can access their older comments by logging into their accounts on Vuukle.