Third desalination plant at Nemmeli will be ready by July: Nehru

Minister reviews progress of the ₹1,516.82-crore project at Nemmeli and asks the CMWSSB officials to complete the work by July; Minister also visits the proposed site at Perur for building a 400 mld desalination plant

January 19, 2023 07:12 pm | Updated 07:12 pm IST - CHENNAI

Minister for Municipal Administration inspecting the work at Nemmeli desalination plant.

Minister for Municipal Administration inspecting the work at Nemmeli desalination plant. | Photo Credit: SPECIAL ARRANGEMENT

The third desalination plant coming up along the East Coast Road at Nemmeli will be ready by July.

Minister for Municipal Administration K.N. Nehru, who reviewed the progress of the ₹1,516.82 -crore project, instructed the Chennai Metropolitan Water Supply and Sewerage Board (CMWSSB) officials to complete the construction of all the components of the project by July. The third plant would have a capacity to treat 150 million litres of seawater daily.  

Work is on to build various units, including seawater intake sump, clarified water tank, dissolved air flotation, ultrafiltration and reverse osmosis pumphouse and limestone filter structure. The Minister reviewed the progress of the offshore work to lay pipelines to draw seawater and discharge brine. The size of the seawater intake pipeline would be about 2,250 mm in diameter.

He inspected the ongoing work to lay 49-km-long pipeline of various diameters — 1,400 mm, 1,200 mm and 300 mm — to cater to the water needs of nearly nine lakh people. Water from the upcoming plant would supply drinking water to Madipakkam, Velachery, Alandur, Medavakkam, Nanmangalam, St. Thomas Mount and the areas in the IT corridor.  

Mr. Nehru visited the site where a 400 mld desalination plant would be constructed at Perur, a few km from Nemmeli desalination plant, at a cost of ₹6,078.40 crore. Rural Industries Minister T.M. Anbarasan, CMWSSB managing director R. Kirlosh Kumar, CMWSSB executive director Raja Gopal Sunkara and Chengalpattu Collector A.R. Rahul Nadh were present.

Earlier, Mr. Nehru inspected the renovation work being taken up at the CMWSSB headquarters in Chintadripet.

0 / 0
Sign in to unlock member-only benefits!
  • Access 10 free stories every month
  • Save stories to read later
  • Access to comment on every story
  • Sign-up/manage your newsletter subscriptions with a single click
  • Get notified by email for early access to discounts & offers on our products
Sign in

Comments

Comments have to be in English, and in full sentences. They cannot be abusive or personal. Please abide by our community guidelines for posting your comments.

We have migrated to a new commenting platform. If you are already a registered user of The Hindu and logged in, you may continue to engage with our articles. If you do not have an account please register and login to post comments. Users can access their older comments by logging into their accounts on Vuukle.