What lies ahead for Vizhinjam port project

LoA to Adani to be issued after EC approval; bid published on VISL website

June 11, 2015 12:00 am | Updated 05:46 am IST - THIRUVANANTHAPURAM:

The Letter of Award (LoA), the first communication from the State government to Adani Ports and Special Economic Zone Ltd. (APSEZ), the private multi-port operator which been selected to build the superstructure and operate the Vizhinjam International Multi-Purpose Seaport, will be issued once the Election Commission (EC) gives its approval.

The LoA will inform the Ahmedabad-based APSEZ that it has been selected for the project and should form a special purpose vehicle (SPV) and give Rs.120 crore as security before signing the concession agreement with the government.

Official sources in the Port Department said Chief Secretary Jiji Thomson had written to the Chief Electoral Officer on Wednesday noon seeking nod for going ahead with the project.

To expedite the take-off of the Mission 676 project, the government has decided to give the LoA once the nod of the Election Commission is obtained. As per the draft concession agreement, the LoA has to be issued within one month to the selected concessionaire.

Officials said time was needed for completing formalities and expressed hope that the project work would kick-off on November 1, Kerala formation day, as announced by Minister for Ports K. Babu.

In another move to ensure transparency, the government published the bid submitted by the APSEZ on the website of VISL after the Cabinet gave its approval.

Mr. Babu said the decision was taken on the basis of legal opinion. With this, all documents relating to the project had been made public.

Adequate measures have been taken to protect the State’s interests with regard to revenue share, port estate development, maintenance, and dredging.

“Not even a single cent of land is sold or leased out,” Chief Minister Oommen Chandy said, adding that the selected private port operator would be given the licence to build and operate by the government.

This would be for 40 years and include four years for construction. The port operator would have to give a share of the total income ranging from 1 per cent from the 15th anniversary of commercial operations of the port and going up to 40 per cent.

Meanwhile, 90 per cent of the 92.75 hectares of land needed for the project as per the draft concession agreement (DCA) has been acquired.

Port estate development will be limited to 30 per cent of the total area of the site.

For rail connectivity, a 17.05-km railway line has to be laid from the Thiruvananthapuram-Kanyakumari line to Vizhinjam.

The railway link to the port will be from Nemom. Rail connectivity to the seaport is needed only from the sixth year as per the draft DCA.

Land for a 2-km road from Thalakkod, 400 metres from Mukkola on the Kazhakuttam-Karode National Highway-66 bypass, to the port has been acquired.

Praise for officials

Mr. Chandy said it was the teamwork by officials led by Ports Principal Secretary James Varghese, VISL CEO and MD A.S. Suresh Babu, successive Chief Secretaries, Planning Board Vice-Chairman K.M. Chandrasekhar, and people’s support that helped the government make the project a reality after 24 years.

0 / 0
Sign in to unlock member-only benefits!
  • Access 10 free stories every month
  • Save stories to read later
  • Access to comment on every story
  • Sign-up/manage your newsletter subscriptions with a single click
  • Get notified by email for early access to discounts & offers on our products
Sign in

Comments

Comments have to be in English, and in full sentences. They cannot be abusive or personal. Please abide by our community guidelines for posting your comments.

We have migrated to a new commenting platform. If you are already a registered user of The Hindu and logged in, you may continue to engage with our articles. If you do not have an account please register and login to post comments. Users can access their older comments by logging into their accounts on Vuukle.