SR commissions double line between Mangaluru Jn., Padil

Railway zone also executes several other improvement works

March 05, 2020 12:04 am | Updated 12:04 am IST - MANGALURU

The upgraded electronic inter-locking and dual visual display unit at Mangaluru Junction.

The upgraded electronic inter-locking and dual visual display unit at Mangaluru Junction.

Southern Railway undertook a host of new works in and around Mangaluru Junction Railway Station to ease movement of trains, including commissioning of the double line between Junction and Padil stations, on Tuesday.

Mangaluru Junction Railway Station has been a crucial junction where trains from three networks — Southern Railway towards South, South Western Railway towards East, and Konkan Railway towards North — meet. As many as 102 passenger train services pass through the junction in a day.

SR’s construction division has undertaken doubling of track between Mangaluru Junction and Panambur Yard via Padil. At present, doubling work on the 17-km stretch between Junction and Padil, excluding 2 km between Kulashekara and Padil that includes 600 m of Kulashekara tunnel, is complete.

The completion, said a release from SR’s Palakkad division, is bound to ease congestion of trains and facilitate their hassle-free movement. Hitherto, connectivity on this stretch for passenger trains was on a single track while trains were subjected to detention for the passing of goods trains.

Upon commissioning the double track for passenger train on Tuesday night, Train No. 12617 Eranakulam Junction–H. Nizamuddin Mangala Express that left Junction at 10.05 p.m. was the first train dealt on the new double line.

Doubling work between Mangaluru Junction and Panambur (21 km), including the tunnel work, is expected to be over by March next, the release said.

Other works

Meanwhile, SR also executed several improvement works in Junction. Platforms 1 to 3 were extended to accommodate 26 coach trains while provision for two-engine lay-bys was provided to facilitate traction change from diesel to electrical and vice versa.

The existing electronic inter-locking signalling system was replaced with upgraded electronic interlocking and dual visual display units at Mangaluru Junction, the release said. Improvement in signalling eases movement of trains.

Provision was also made for continuous track circuiting between Junction and Padil to ease movement of trains and ensure safety while trip shed and ballast siding were provided at Junction.

0 / 0
Sign in to unlock member-only benefits!
  • Access 10 free stories every month
  • Save stories to read later
  • Access to comment on every story
  • Sign-up/manage your newsletter subscriptions with a single click
  • Get notified by email for early access to discounts & offers on our products
Sign in

Comments

Comments have to be in English, and in full sentences. They cannot be abusive or personal. Please abide by our community guidelines for posting your comments.

We have migrated to a new commenting platform. If you are already a registered user of The Hindu and logged in, you may continue to engage with our articles. If you do not have an account please register and login to post comments. Users can access their older comments by logging into their accounts on Vuukle.