CIAL breathes easy with flood control measures in place

Thirteen completed projects keep airport dry despite rising water level in Periyar

August 09, 2020 12:25 am | Updated 12:25 am IST - KOCHI

All on track:  Work on diversion of the canal on the southern side of the airport runway at Nedumbassery in progress. The  runway is  seen in the background .

All on track: Work on diversion of the canal on the southern side of the airport runway at Nedumbassery in progress. The runway is seen in the background .

The Cochin International Airport (CIAL) authorities are breathing easier this year when compared to August 2018 and 2019, with half of the 26 projects, costing more than ₹129 crore, to prevent flooding of the airport facilities and four neighbouring panchayats being completed.

“We passed last week a crucial test on the ability of the newly commissioned projects to help prevent flooding,” airport sources said on Saturday, pointing out that as many as 13 completed projects had kept the airport and neighbouring panchayats dry, even though the water level in the Periyar went up to 7.5 metres above sea level by 9 p.m. on Thursday as measured at the Central Water Commission facility at Neeleeswaram.

Seven metres is a flood-like situation as was experienced by Nedumbassery and neighbouring panchayats in 2019.

The water level had gone up to 12 metres in 2018, airport sources said on Saturday.

While the first phase of the August rain has boosted the confidence of the CIAL authorities, they are keeping their fingers crossed for the remaining part of the season.

Heavy flooding of its facilities in 2018 had resulted in the airport being shut down for 15 days, causing a loss of around ₹160 crore. The airport was shut again for around 50 hours in August last year owing to flooding.

The projects being undertaken include development of infrastructure in the neighbouring panchayats and measures to ensure that the panchayats do not get isolated due to flooding in the future. Two key bridges, diversion of Chengalthode and its widening, declogging several stretches of storm water passages, demolition of old structures that prevent free flow of water are some of the initiatives.

The key component is the work on widening Chengalthodu on the northern side of the runway and the diversion of the canal on the southern side.

These projects are undertaken with the full participation of people, airport sources said.

0 / 0
Sign in to unlock member-only benefits!
  • Access 10 free stories every month
  • Save stories to read later
  • Access to comment on every story
  • Sign-up/manage your newsletter subscriptions with a single click
  • Get notified by email for early access to discounts & offers on our products
Sign in

Comments

Comments have to be in English, and in full sentences. They cannot be abusive or personal. Please abide by our community guidelines for posting your comments.

We have migrated to a new commenting platform. If you are already a registered user of The Hindu and logged in, you may continue to engage with our articles. If you do not have an account please register and login to post comments. Users can access their older comments by logging into their accounts on Vuukle.