Brahmapuram lacks enough space for proper treatment of waste, says High Court-appointed panel

The report was submitted to the High Court along with photos and videos of the Brahmapuram plant and the site

March 13, 2023 10:53 pm | Updated March 14, 2023 07:46 am IST - KOCHI

The committee pointed out that the available area for the windrow composting plant at Brahmapuram was not adequate to treat the huge quantity of waste brought to the site

The committee pointed out that the available area for the windrow composting plant at Brahmapuram was not adequate to treat the huge quantity of waste brought to the site

The high-level committee appointed by the Kerala High Court pointed out that the available area for the windrow composting plant at Brahmapuram was not adequate to treat the huge quantity of waste brought to the site, and that the existing building at the site was in a dilapidated state and might collapse any time.

The report was submitted to the High Court along with photos and videos of the Brahmapuram plant and the site. It said that in view of the exorbitant cost involved in renovating the existing plant, the Kochi Corporation had decided to construct a new windrow composting plant. The proposal is under the government’s consideration. In fact, 10 acres had been set apart for the project. 

As for legacy waste processing, the report said that that legacy waste was being processed using biomining techniques. But the capacity of the machinery at the site for biomining is not adequate for completion of work within the stipulated timeframe. The segregation and sorting of legacy waste at the site were not in accordance with the Central Pollution Control Board guidelines. The infrastructure at the plant is not sufficient to treat non-biodegradable waste. No scientific management of waste was observed at the site.

Since no material-wise segregation has taken place at the plant, the refuse-derived fuel (RDF), which is one of the main end-products of biomining, is of inferior quality. As result, it is not being accepted by cement factories. The RDF generated after biomining has not been transported from Brahmapuram. The quality of good earth discharge is also poor owing to lack of proper segregation.

0 / 0
Sign in to unlock member-only benefits!
  • Access 10 free stories every month
  • Save stories to read later
  • Access to comment on every story
  • Sign-up/manage your newsletter subscriptions with a single click
  • Get notified by email for early access to discounts & offers on our products
Sign in

Comments

Comments have to be in English, and in full sentences. They cannot be abusive or personal. Please abide by our community guidelines for posting your comments.

We have migrated to a new commenting platform. If you are already a registered user of The Hindu and logged in, you may continue to engage with our articles. If you do not have an account please register and login to post comments. Users can access their older comments by logging into their accounts on Vuukle.