Delays plague two elevated corridors of SRDP

As fund releases for the steel flyovers have been paltry so far, it could easily take two more years for completion

October 28, 2021 12:07 am | Updated 12:07 am IST - HYDERABAD

Infrastructural development works taken up in the city under the Strategic Road Development Plan (SRDP) may face inordinate delays due to gaps in fund release.

While several works are under way at different locations in the city as part of the SRDP, especially to be affected by the fund crunch are the two elevated corridors coming up respectively between Indira Park and VST Junction, and between Nalgonda Crossroads and Owaisi Junction. Both the flyovers were designed as steel bridges, with steel being used instead of RCC for casting major part of the structure.

Steel was chosen for speedy completion of the works, but as irony would have it, the steel component in the design is proving to be a hurdle in terms of funding. “Steel parts have to be ordered to design from SAIL (Steel Authority of India Limited), and unless full payment is made, they will not send the consignment. Fund releases have been paltry so far, hence it could easily take two more years for the bridges to take final shape,” an official shared under the condition of anonymity.

Though getting government sanction way back in 2018, the flyovers had been delayed due to various reasons. Tenders were finalised only last year, and the projects were launched in July, 2020.

The 2.61-kilometre four-lane bidirectional elevated corridor between Indira Park and VST has been designed with an estimated cost of ₹ 350 crore. It will help commuters to avoid four junctions namely at NTR Stadium, Ashoknagar, RTC Crossroads and Baghlingampally junction.

The four-lane bidirectional corridor between Nalgonda crossroads and Owaisi Junction will be of 3.382 kilometres length, and an estimated cost of ₹ 523.37 crore. It will pass via Saidabad, IS Sadan, Chanchalguda and Dhobighat junctions, thereby reducing traffic delays.

Delay in completion of the flyovers could cause enormous traffic inconvenience, as roads have been dug up at both locations for laying of foundations. Already, commuters are facing severe hardships negotiating their way through the narrow strip of road on the VST-Indira Park stretch.

“Each of these projects needs release of about ₹ 30 crore per month for completion before the deadline next year. As of now, the releases do not cross ₹4 crore to ₹5 crore per month,” informed the official.

0 / 0
Sign in to unlock member-only benefits!
  • Access 10 free stories every month
  • Save stories to read later
  • Access to comment on every story
  • Sign-up/manage your newsletter subscriptions with a single click
  • Get notified by email for early access to discounts & offers on our products
Sign in

Comments

Comments have to be in English, and in full sentences. They cannot be abusive or personal. Please abide by our community guidelines for posting your comments.

We have migrated to a new commenting platform. If you are already a registered user of The Hindu and logged in, you may continue to engage with our articles. If you do not have an account please register and login to post comments. Users can access their older comments by logging into their accounts on Vuukle.