Water supply improvement work to proceed at a slow pace until election

Coimbatore Corporation has verbally instructed Suez to stop digging roads

February 16, 2021 12:34 am | Updated 12:37 am IST - Coimbatore

Suez Projects Pvt. Ltd is executing the ₹ 2,972.16 crore project to revamp the water distribution network and to maintain the revamped distribution lines for 21 years in  60 wards.

Suez Projects Pvt. Ltd is executing the ₹ 2,972.16 crore project to revamp the water distribution network and to maintain the revamped distribution lines for 21 years in 60 wards.

In the next few months or until election, the 24x7 drinking water supply augmentation project is likely to proceed at a slow pace.

Sources involved with the project execution said the Coimbatore Corporation authorities had asked the company executing the project, Suez Projects Pvt. Ltd., to go slow so that it did not have to dig roads ahead of election.

The company is executing the ₹ 2,972.16 crore project to revamp the water distribution network and take care of maintenance of the revamped distribution lines for 21 years in the old city area of 60 wards.

The sources said the logic offered for going slow and not digging roads was to not inconvenience the public, which could perhaps show the anger of having to drive on bad roads at polling booth.

The Corporation’s verbal instruction to the company came at a time when it had mobilised labourers after the COVID-19 lockdown to improve the pace of execution, the sources said.

As of February 2020, when the company is in the second year of the four-year execution period, it had completed only 10% work. Even in R.S. Puram, where the company had first started the work over two years ago, it was left with at least a couple of hundred house service connections.

It had completed laying the main distribution line work in SIHS Colony, Singanallur, Ukkadam, Telugupalayam and a couple of other areas. Or in other words, it had completed most of the work in around 10 of the 100 district metering areas in the 60 wards.

The Corporation and the company had divided the 60 wards in to district metering zones as a part of its execution plan.

The sources also said that when the company accelerates the pace of work after election in May, it would have a window period of a month or two before the South West Monsoon sets in and thereafter the North East Monsoon.

This invariably meant that the company would not be in a position to complete work within the stipulated four-year period, they added.

0 / 0
Sign in to unlock member-only benefits!
  • Access 10 free stories every month
  • Save stories to read later
  • Access to comment on every story
  • Sign-up/manage your newsletter subscriptions with a single click
  • Get notified by email for early access to discounts & offers on our products
Sign in

Comments

Comments have to be in English, and in full sentences. They cannot be abusive or personal. Please abide by our community guidelines for posting your comments.

We have migrated to a new commenting platform. If you are already a registered user of The Hindu and logged in, you may continue to engage with our articles. If you do not have an account please register and login to post comments. Users can access their older comments by logging into their accounts on Vuukle.