Drinking water once in two days for Salem City is still a dream 

June 07, 2022 06:03 pm | Updated 06:03 pm IST

Residents of Subramania Nagar in Salem waiting for their turn at public water tap on Tuesday.

Residents of Subramania Nagar in Salem waiting for their turn at public water tap on Tuesday. | Photo Credit: E. LAKSHMI NARAYANAN

The civic body that promised to supply drinking water once in two days, even after implementation of a dedicated water supply scheme, still remains a dream for the residents. 

Considering the population increase and need for protected drinking water in all the 60 wards, during the DMK regime in 2010, the Salem-Mettur Dedicated Water Supply Scheme was announced at a cost of ₹320 crore. The work was divided into two phases. The first phase estimated to the tune of ₹188.48 crore, includes construction of a new water treatment plant, a water pumping station at Thottilpatti and laying pipelines from Mettur to Salem Corporation with entry point at Mamangam.

The second phase, estimated to the tune of ₹132.48 crore, includes laying pipe lines in all 60 wards, linking pipelines, testing water and construction of 22 over tanks in the city. The work order for the first phase works was issued on August 27, 2010 and it was scheduled to be completed by August 2012. But due to various reasons, including permission delayed by National Highway Authority of India (NHAI) to lay pipelines on the NH, the work was delayed. 

The work for the first phase was finally completed in June 2014. After five years, in 2019, the second phase of work was also completed. But still, people in most of the wards in city receive drinking water once a week or ten days. Some wards in Hasthampatti zone receive water once in three days. 

Speaking to The Hindu, S. Prabhu, a resident, said “we are receiving water twice or thrice a month”. When we petitioned the corporation officials, they claimed various technical reasons” . 

Former leader of the opposition in the corporation council, M. Bhuvaneswari, said the scheme aims to supply water once in two days. As this scheme was brought by the DMK government, the works were done at a slow pace during the AIADMK regime.

She also alleged irregularities in laying new pipelines and water was still being supplied in old pipelines. So only people are unable to receive water in the correct interval. The State government should form a commission to inquire about irregularities in the scheme, she added. 

City Engineer G Ravi said that per day 130 MLD of water was supplied to the people from this scheme. 

Mayor A. Ramachandran said that he had held discussions with officials thrice. But still we are unable to find the answer why water could not be supplied, even though the scheme works are completed and we have adequate water in Mettur. Soon an inquiry would be conducted and erring officials would be brought to justice, the Mayor said.

Ends.

0 / 0
Sign in to unlock member-only benefits!
  • Access 10 free stories every month
  • Save stories to read later
  • Access to comment on every story
  • Sign-up/manage your newsletter subscriptions with a single click
  • Get notified by email for early access to discounts & offers on our products
Sign in

Comments

Comments have to be in English, and in full sentences. They cannot be abusive or personal. Please abide by our community guidelines for posting your comments.

We have migrated to a new commenting platform. If you are already a registered user of The Hindu and logged in, you may continue to engage with our articles. If you do not have an account please register and login to post comments. Users can access their older comments by logging into their accounts on Vuukle.