Chennai airport expansion yet to achieve goals

Mired in delays, the nearly Rs. 2,000-crore project is well past its deadline

January 11, 2014 07:01 am | Updated May 13, 2016 08:47 am IST - CHENNAI:

Five months after the departure operations at the new international terminal began, the arrival hall has still not been commissioned. Photo: M. Srinath

Five months after the departure operations at the new international terminal began, the arrival hall has still not been commissioned. Photo: M. Srinath

What started in 2008 as massive expansion of Chennai airport hit several roadblocks, was repeatedly marred by delays and today, two years well past its deadline, the project is incomplete.

The project, launched five years ago, setting 2011 as the deadline, comprised construction of new domestic and international terminals, extension of the secondary runway over Adyar river, construction of additional parking bays and a new category fire station.

The cost of the project was increased from Rs. 1,808 crore to a little over Rs. 2,000 crore.

The new domestic and international terminals were inaugurated in January 2013 and thrown open for use by April and August, respectively, in a phased manner.

Five months after the departure operations at the new international terminal began, the arrival hall has still not been commissioned.

AAI chairman V.P. Agrawal said, “It is taking time to commission the arrival hall at the new international terminal because of inadequate Customs and Central Industrial Security Force staff.”

The secondary runway, whose extension from 1,032 metres to 2,032 metres cost about Rs. 450 crore, awaits clearance from the Directorate General of Civil Aviation (DGCA), two years after its completion, said an official of Airports Authority of India.

The secondary runway, once operationalised, can support the main runway with an ability to handle five aircrafts per hour, and also undertake flight operations in case of an emergency on the main runway, he said.

“We are holding discussions with DGCA officials to operationalise the secondary runway soon,” said Mr. Agrawal

A recent government audit report noted there was a loss of interest of Rs. 190 crore over the secondary runway. The report also pointed to several losses incurred owing to delays in the project including delay in the commissioning of new terminals and the fire station.

0 / 0
Sign in to unlock member-only benefits!
  • Access 10 free stories every month
  • Save stories to read later
  • Access to comment on every story
  • Sign-up/manage your newsletter subscriptions with a single click
  • Get notified by email for early access to discounts & offers on our products
Sign in

Comments

Comments have to be in English, and in full sentences. They cannot be abusive or personal. Please abide by our community guidelines for posting your comments.

We have migrated to a new commenting platform. If you are already a registered user of The Hindu and logged in, you may continue to engage with our articles. If you do not have an account please register and login to post comments. Users can access their older comments by logging into their accounts on Vuukle.