Trial run of new sewage treatment plants next month

Sewer line connections can only be completed after monsoon

July 08, 2014 12:30 pm | Updated 12:30 pm IST - MANGALORE:

Sewer line connections can only be completed after monsoon.

Sewer line connections can only be completed after monsoon.

Residents in some parts of the city will have to wait till October to connect sewer lines of their houses to manholes though a vast network of sewer lines and associated facilities constructed by the government under Asian Development Bank (ADB) loan will be ready by this month-end.

Because road cutting was not allowed in the monsoon, people would have to wait for the rain to stop to connect the lines to manholes, according to officials.

Of the 355 km-long network of underground sewer lines – construction of which began a decade ago – 155 km-long network was pending to be commissioned due to delay in laying electricity connection lines to sewage treatment plants (STPs) at Jeppinamogaru and Surathkal.

M. Yashwant Raj, Executive Engineer, Karnataka Urban Development and Coastal Environmental Management Project (KUDCEMP), told The Hindu that overhead power lines connecting the STP at Jeppinamogaru to a distance of about 300 m was pending to be laid near Bajal. Air budged power cable to about 1km distance was pending to be laid (hung) to connect the STP at Surathkal. These works would be over by the end of this month. “We will trial run the Jeppinamogaru and Surathkal STPs next month,” he said.

A 65 km-long sewer line from Shivabagh, Maroli, Tarethota, Pumpwell, Yekkur, Jeppinamogaru, Bajal and surrounding areas were connected to the STP at Jeppinamogaru with a processing capacity of 20 MLD (million litres a day).

Another 90 km-long underground pipeline from Hosabettu, Kulai, Katipalla and Surathkal were connected to the 16.5 MLD-capacity STP at Surathkal.

Mr. Raju said that permission of the Southern Railway and Konkan Railway Corporation Ltd. would have to be obtained before commissioning the lines as at Yekkur and near Surathkal, the sewer lines passed below the railway lines.

He said that 200 km-long network of pipelines connecting the STPs at Kavoor and Pachchanady under the project have been commissioned.

0 / 0
Sign in to unlock member-only benefits!
  • Access 10 free stories every month
  • Save stories to read later
  • Access to comment on every story
  • Sign-up/manage your newsletter subscriptions with a single click
  • Get notified by email for early access to discounts & offers on our products
Sign in

Comments

Comments have to be in English, and in full sentences. They cannot be abusive or personal. Please abide by our community guidelines for posting your comments.

We have migrated to a new commenting platform. If you are already a registered user of The Hindu and logged in, you may continue to engage with our articles. If you do not have an account please register and login to post comments. Users can access their older comments by logging into their accounts on Vuukle.