MESCOM getting ready to cater to energyrequirements for the next two decades

220 kV power station at Kottara, 110 kV stations at four places planned

December 25, 2016 12:57 am | Updated 12:57 am IST - MANGALURU:

MESCOM Managing Director Chikkananjappa

MESCOM Managing Director Chikkananjappa

Considering the pace at which Mangaluru is growing, Mangalore Electricity Supply Company (MESCOM) has drawn up plans to cater to energy requirements of the city for the next two decades.

One 220 kV power station at Kottara and one each 110 kV power stations at Nehru Maidan, Thokkottu, Arkula and Jeppinamogaru would be built by Karnataka Power Transmission Corporation Ltd. to cater to the increasing energy demand in the urban area, said MESCOM Managing Director Chikkananjappa here on Friday.

He was addressing a meet-the-press programme jointly organised by the Dakshina Kannada Union of Working Journalists and the Mangaluru Press Club. Besides catering to Mangaluru, the company has proposed new 33/11 kV sub-stations at Malpe, Venur, Kalladka, Byakodu, Kavu, Kollur and Guthigar, he said.

Underground cabling

Though there is a demand and a need for taking power lines underground in the city, Mr. Chikkananjappa said, there were also doubts whether this was possible. As a majority of the roads have been concreted without leaving ducts to draw cables, the move would involve cutting open the concrete roads, he said.

However, if the government is keen on taking all power lines underground, a solution has to be jointly worked out with the Mangaluru City Corporation, he said.

Online bill payment

Mr. Chikkananjappa said that at present online bill payment facility is available in 11 towns under MESCOM jurisdiction. Another 18 towns would be added after the completion of the Integrated Power Development Scheme (IPDS).

The entire MESCOM network, including rural areas, could be brought under online payment once the company completed GIS (geographical information system) mapping of its entire network, which might take about one-and-a-half years, he said.

Capacity added

In the last two years, the company has added 4,200 route km of HT and 4,000 route km of LT lines to its network besides adding 12,000 transformers. Four new sub-stations were commissioned and the capacity of another four was augmented.

About 80 new feeders were added besides servicing 256 solar roof-top installations to generate 3.2 MW power.

Eight new sub-divisions were formed, while 33 new section offices, 62 service stations were opened and 2,450 new posts were created. As the company had severe staff crunch, 2,300 assistant and junior linesmen were recruited besides employing 90 engineers and accountants, he said.

0 / 0
Sign in to unlock member-only benefits!
  • Access 10 free stories every month
  • Save stories to read later
  • Access to comment on every story
  • Sign-up/manage your newsletter subscriptions with a single click
  • Get notified by email for early access to discounts & offers on our products
Sign in

Comments

Comments have to be in English, and in full sentences. They cannot be abusive or personal. Please abide by our community guidelines for posting your comments.

We have migrated to a new commenting platform. If you are already a registered user of The Hindu and logged in, you may continue to engage with our articles. If you do not have an account please register and login to post comments. Users can access their older comments by logging into their accounts on Vuukle.