R&B roadblocks substations in Hyderabad

Swathi V.
Comment (1)   ·   print   ·   T  T  

Lack of road cutting permissions delay power supply

As is natural for a city of Hyderabad’s stature, there is increasing demand for new power connections. But with authorities delaying permission for road cutting, so that input lines may be laid, the charging of substations is being delayed.

Cases in point are the 33 and 11KV substations near the Koti Women’s College and the Nizam College respectively, which, despite having been complete in all civil works, are still waiting to be charged for want of input lines.

“We need to cut the road to lay underground cable lines and despite repeated requests to the Roads and Buildings (R&B) Department, we are not getting the necessary permissions,” say CPDCL officials.

The substation near Nizam College needs to get its supply from the 132/33 KV Hussainsagar substation, for which, a 33KV cable line needs to be laid via Secretariat.

“The stretch from Nizam College up to the Telugu Talli flyover belongs to the GHMC, and we could finish the works on this stretch. However, for carrying out works from the flyover up to the Mint Compound, we need permissions from the R&B, which are hard to come by,” says a Superintendent Engineer.

Similar is the case with the Koti Women’s College substation, which needs its input supply from the Imlibun substation.

But the stretch from Imlibun to Chaderghat has been hanging fire with no nod yet from R&B officials.

Though requests were placed with R&B officials way back in December 2011— as soon as the Letters of Intent were issued — a nod from the department is yet to arrive, they said.

Also pending for a few months is another request for clearance to interlink lines between Sivarampally and Chandulal Baradari substations.

CPDCL officials say the delay has to do with the payment of road cutting charges directly to the R&B department, instead of routing them through contractors. Payment through contractors allowed scope for collusion between them and the engineers, which is not possible now, they say.

With construction of each substation costing around Rs.11 crore, the pending road cutting permissions are resulting in locked investment for CPDCL.

Work is currently on for 24 substations within the Metro Zone, officials added.

More In: Hyderabad

Hyderabad is the only major city in India where substations in colonies are placed on footpaths or roads. There are several instances where even GHMC public gardens can be used to house electric substations, but this never happens. A small time christian convert may set up a church or a hindu or muslim come up with a make shift temple/masjid which will either be ignored by GHMC or even encouraged but do not permit installation of a substation! So Electricity Dept. like beggars are left to occupy a place where no one will object to their most important structure for electric supply

from:  M Sitaram
Posted on: Apr 29, 2013 at 06:16 IST
This article is closed for comments.
Please Email the Editor

Vijayawada

Visakhapatnam

Hyderabad Connect Newsfeed


O
P
E
N

close

Recent Article in Hyderabad