Metro rail overbridge at Begumpet completed

‘Bridge builder’ method used for ROB construction

July 08, 2017 11:07 pm | Updated July 09, 2017 11:49 am IST - HYDERABAD

Hyderabad metro rail authorities speed up their work on Rail overbridges.

Hyderabad metro rail authorities speed up their work on Rail overbridges.

The Hyderabad Metro Rail has said that its rail overbridge (ROB) over the railway lines at Begumpet and the adjacent railway station was successfully completed, closing a critical gap in corridor III of the project.

With this and completion of the Oliphenta bridge near Secunderabad railway station (expected to be done in a few weeks), the extension of the eight km stretch of the Nagole – Mettuguda metro line up to Begumpet has become feasible.

The construction of the bridge was taken up under highly challenging conditions given the railway lines and the station below were busy round the clock, a release of HMR said.

The total length of ROB was 450 ft. It was a curve, wedged between Begumpet flyover on one side and several buildings on the other. A special method called “bridge builder” was used in the construction in view of the curved nature of ROB, for a height of 60 ft from a narrow road and railway lines below.

HMR managing director N.V.S. Reddy said in the release that erection and movement of the bridge builder device, weighing 100 metric tonnes, was an engineering nightmare.

Pre-cast segments of the builder were lifted with heavy duty cranes, taking all safety precautions and not causing traffic disruption.

To meet multiple technical challenges, the bridge builder was specially built and load test performed at the Uppal casting yard before it was brought to Begumpet and mounted on the already built metro viaduct from Varun Motors and Country Club sides.

The whole metro ROB was built in three parts with the main portion (span) coming up over railway lines and the railway station.

The two ends were 130 ft and 107 ft respectively. After erecting the bridge builder on both sides, it was anchored safely with counter weights.

The Indian Railways gave only ‘three hour blocks’ for launching each segment by stopping trains beyond midnight once a week.

0 / 0
Sign in to unlock member-only benefits!
  • Access 10 free stories every month
  • Save stories to read later
  • Access to comment on every story
  • Sign-up/manage your newsletter subscriptions with a single click
  • Get notified by email for early access to discounts & offers on our products
Sign in

Comments

Comments have to be in English, and in full sentences. They cannot be abusive or personal. Please abide by our community guidelines for posting your comments.

We have migrated to a new commenting platform. If you are already a registered user of The Hindu and logged in, you may continue to engage with our articles. If you do not have an account please register and login to post comments. Users can access their older comments by logging into their accounts on Vuukle.