Kudankulam reactor turbine stopped again

‘It may take five days for operations to resume’

October 30, 2013 04:08 am | Updated November 16, 2021 07:39 pm IST - TIRUNELVELI (TAMIL NADU):

The turbine of the Kudankulam Nuclear Power Project’s first reactor which was resynchronized with the southern gridlast Friday, was stopped again on Tuesday “for a series of mandatory tests”.

After the 1,000 MWe capacity reactor was synchronised with the grid for the first time with 160 MWe, last Tuesday at 2.45am, it was stopped at 5.40am the same day for tests stipulated by the Atomic Energy Regulatory Board (AERB). As the test results submitted to the AERB were found to be satisfactory, the ‘Operational Team’ of the KKNPP was given the green signal to resynchronize the turbine again on Friday night.

Since then, the turbine has been operational in order to generate electricity up to 300 MWe. “As we reached 300 MWe, we stopped the turbine manually for mandatory tests at 8pm,” confirmed Site Director, KKNPP, R.S. Sundar.

Sources in the KKNPP said it might take a minimum of five days for resuming turbine operations.

0 / 0
Sign in to unlock member-only benefits!
  • Access 10 free stories every month
  • Save stories to read later
  • Access to comment on every story
  • Sign-up/manage your newsletter subscriptions with a single click
  • Get notified by email for early access to discounts & offers on our products
Sign in

Comments

Comments have to be in English, and in full sentences. They cannot be abusive or personal. Please abide by our community guidelines for posting your comments.

We have migrated to a new commenting platform. If you are already a registered user of The Hindu and logged in, you may continue to engage with our articles. If you do not have an account please register and login to post comments. Users can access their older comments by logging into their accounts on Vuukle.