Land acquisition for bridge projects to be expedited in Chennai

The bridge project in Vadaperumbakkam requires acquisition of 14 private lands. Administrative sanction has been obtained on September 12 and the officer to carry out the acquisition process has also been appointed by the Chennai Collector, say officials

Updated - October 13, 2023 03:15 am IST

Published - October 12, 2023 08:17 pm IST - CHENNAI

Chennai, Tamilnadu, 12/10/2023: View of the Valluvar Kottam junction on Thursday. Photo: VEDHAN M / THE HINDU

Chennai, Tamilnadu, 12/10/2023: View of the Valluvar Kottam junction on Thursday. Photo: VEDHAN M / THE HINDU | Photo Credit: VEDHAN M

With Chennai Corporation asking the Chennai Collectorate to expedite the land acquisition process for bridge projects in various zones, officials said this would speed up the works.

The bridge project in Vadaperumbakkam requires acquisition of 14 private lands covering an area of 13,218 sq.ft. for the ramp portion of the work. Administrative sanction for land acquisition has been obtained on September 12, 2023. The officer for land acquisition has been appointed by the Chennai Collector. The bridge construction has already started and 74% of the project work has been completed across Puzhal surplus water canal at Vadaperumbakkam in Division 17, Manali Zone.

The project is estimated at ₹22.4 crore and has been taken up under Chennai Mega City Development Mission in 2018-2019. “Bridge work will be completed in three months from the date of completion of land acquisition. We have to shift 900 mm diameter waterline for the project,” said an official.

The project for constructing a bridge at Valluvar Kottam junction in Nungambakkam will also be expedited. The estimate for the project has been revised from ₹176 crore to ₹195.19 crore due to changes in the Land Plan Schedule. At least 1.17 lakh sq. ft. of land, including 30,784 sq. ft. of private land, is required for the project.

The officer to carry out the land acquisition has been appointed by the Collector. An agency is expected to conduct Social Impact Assessment and prepare a Social Impact Management Plan. “We will call for tenders after completion of land acquisition near Valluvar Kottam,” said an official.

The acquisition of 47,318 sq. ft. of land is required for the construction of a high-level bridge across the Cooum at Chinna Nolambur connecting Poonamallee High Road and Union Road in Division 143 and 144, in Valasaravakkam Zone.

An area measuring 16,479 sq. ft. of land is required for the bridge at Sannathi First Cross Street. The construction of a road-overbridge (ROB) in lieu of the existing level crossing No. 2B at Manali Road in Division-41 in Tondiarpet Zone is undertaken.

The construction of bridge across Adambakkam Lake at Jeevan Nagar Second Street in Alandur Zone requires removal of encroachment along Medavakkam Main Road.

Reconstruction of the bridge across Otteri Nullah connecting Aspiran Garden II Street and Kilpauk Garden Road , flyover along South Usman Road and CIT Nagar First Main Road and a flyover over the existing subway at Ganesapuram near Vyasarpadi, Jeeva Railway Station in Tondiarpet and Thiru Vi Ka Nagar are all expected to be completed in September 2024, officials said.

0 / 0
Sign in to unlock member-only benefits!
  • Access 10 free stories every month
  • Save stories to read later
  • Access to comment on every story
  • Sign-up/manage your newsletter subscriptions with a single click
  • Get notified by email for early access to discounts & offers on our products
Sign in

Comments

Comments have to be in English, and in full sentences. They cannot be abusive or personal. Please abide by our community guidelines for posting your comments.

We have migrated to a new commenting platform. If you are already a registered user of The Hindu and logged in, you may continue to engage with our articles. If you do not have an account please register and login to post comments. Users can access their older comments by logging into their accounts on Vuukle.