Work on STP at Kaggadasapura lake to begin

The lake is prone to frothing much like Bellandur and Varthur lakes

Published - September 16, 2020 09:48 pm IST

Residents attribute frothing in Kaggadasapura lake to two drains, which they say, let untreated sewage into the water body.

Residents attribute frothing in Kaggadasapura lake to two drains, which they say, let untreated sewage into the water body.

Kaggadasapura lake in east Bengaluru, which is prone to frothing much like Bellandur and Varthur lakes, will get some respite. The Bangalore Water Supply and Sewerage Board (BWSSB) will soon begin construction of a 5 MLD capacity Sewage Treatment Plant (STP) near the lake. The groundbreaking ceremony of the STP is slated to be held on Thursday.

Residents attribute the frothing to two drains, which they say, let untreated sewage into the lake.

“The project, which has a budget of ₹26.38 crore, will take 18 months to complete. Once the STP is completed and commissioned, the health and ecology of the lake will automatically improve,” said Gangadhar B.C., chief engineer (wastewater management), BWSSB.

Meanwhile, work order for construction of a 7 MLD STP at Puttenahalli lake in Hebbal valley was issued recently.

“Both these projects – STPs at Kaggadasapura and Puttenahalli lakes – were proposed under the guidance of the Karnataka State Pollution Control Board,” he said.

But for the lake to be rejuvenated, residents in and around the area said the authorities simultaneously need to crack down on indiscriminate dumping of construction and demolition waste.

S. Raghu., MLA, C.V. Raman Assembly constituency, said that it was a long-standing demand of citizens and activists. “Along with construction of STP, we will also begin rejuvenation of the lake. ₹8.6 crore has been sanctioned in this regard,” he said.

According to Mr. Gangadhar, the STP will help in the rejuvenation, maintenance and protection of not just of Kaggadasapura lake but also Bellandur and Varthur lakes as all three fall under the K.C. Valley system.

Another senior BWSSB official said that three STPs linked to Bellandur and Varthur lakes – 5 MLD STP at Sarakki, 10 MLD STP at Hulimavu and 35 MLD STP at Agaram – have been commissioned.

“Five MLD STP at Chikkabeguru is completed and will be commissioned by the end of September. The wastewater wet well of 32.5 MLD near the premises of the 90 MLD Bellandur Amanikere STP will be completed by March 2021,” the official said.

0 / 0
Sign in to unlock member-only benefits!
  • Access 10 free stories every month
  • Save stories to read later
  • Access to comment on every story
  • Sign-up/manage your newsletter subscriptions with a single click
  • Get notified by email for early access to discounts & offers on our products
Sign in

Comments

Comments have to be in English, and in full sentences. They cannot be abusive or personal. Please abide by our community guidelines for posting your comments.

We have migrated to a new commenting platform. If you are already a registered user of The Hindu and logged in, you may continue to engage with our articles. If you do not have an account please register and login to post comments. Users can access their older comments by logging into their accounts on Vuukle.