Lack of dedicated transformers affect water projects in Mandya district

Updated - May 07, 2016 05:44 am IST

Published - May 07, 2016 12:00 am IST - Mandya:

Of the 3,912 water projects, only 2,146 have been fixed with such transformers

Tough days:According to an official, Rs. 52.24 crore is needed to procure and install dedicated transformers to all the water projects in Mandya district.

Contingency measures to ensure drinking water supply to the parched areas in the district is likely to be hit owing to non-installation of dedicated transformers to the water projects in the district.

The district has been declared drought hit for the second consecutive year and a majority of the water bodies have gone dry. As over 85 villages have been facing water shortage, the Mandya district administration has launched various measures—including installation of dedicated transformers to the water projects— to address the crisis. However, these water projects have been affected owing to shortage of transformers.

There are 3,912 multi-village water and piped water projects spread across the seven taluks in the district. Of them, only 2,146 projects are installed with dedicated transformers and the remaining 1,766 have been depending on the existing transformers installed in nearby areas for streetlights and domestic connections, a senior official at the Chamundeshwari Electricity Supply Corporation told

ADVERTISEMENT

The Hindu here on Friday. “We need at least Rs. 52.24 crore to procure and install dedicated transformers to all the water projects,” he said. The Chamundeshwari Electricity Supply Corporation has already submitted a proposal in this regard to the Zilla Panchayat, a senior CESC official said.

ADVERTISEMENT

According to Chandrahas, Executive Engineer (in-charge), Zilla Panchayat, the civic body has submitted a Rs. 7.89 crore proposal to the State government to install transformers and electrical cables to the water projects. The CESC is taking steps to supply power to the water projects through the existing transformers. But, chances of tripping during overloads are high. Also, water cannot be supplied during load shedding and because of low voltage. Hence, every project needs dedicated transformers, another senior Zilla Panchayat official told

The Hindu.

CESC has been supplying power to

the water projects using the existing transformers

This is a Premium article available exclusively to our subscribers. To read 250+ such premium articles every month
You have exhausted your free article limit.
Please support quality journalism.
You have exhausted your free article limit.
Please support quality journalism.
The Hindu operates by its editorial values to provide you quality journalism.
This is your last free article.

ADVERTISEMENT

ADVERTISEMENT