Transmission loss adds to power woes

June 07, 2014 09:40 am | Updated November 17, 2021 02:34 am IST - KOCHI:

The Power Grid Corporation of India’s 400-kV transmission line between Kochi and Edamon, connecting Tirunelveli to draw power from the Kudankulam nuclear power plant, is yet to be completed. Though power generation from the nuclear plant has already commenced, Kerala is constrained to draw its share through a circuitous route now, resulting in transmission losses.

Ministerial-level talks Talks held at the ministerial level to sort out the issue of acquiring right of way through private landholdings in districts such as Pathanamthitta and Kottayam have only been partially successful, according to sources.

Benny Behanan, MLA, who was involved in the talks convened by the Chief Minister in the past, said the issue was expected to be resolved soon. A senior Kerala State Electricity Board official told

ADVERTISEMENT

The Hindu that Kerala was receiving power from the nuclear plant through an alternative route, Tirunelveli- Udumalpet- Areekode- Madakkathara. It stretches about 250 km more in length in comparison to the Tirunerlveli- Edamon- Kochi- Madakkathara route.

ADVERTISEMENT

The corporation has a 400-kV transmission station at Areekode, Kozhikode, on the Mysore-Areekode line. A 400-kV substation existing at Pallippuram, Thiruvananthapuram, will enable the State to have a 400-kV power highway once the Edamon-Kochi line gets completed.

The power highway will connect the State to the national grid, facilitating power transmission from various locations in the grid to satisfy Kerala’s needs appropriately.

ADVERTISEMENT

Route survey

ADVERTISEMENT

ADVERTISEMENT

The drawing of power from the Kudankulam nuclear power station was planned a decade ago. A route survey was conducted and the KSEB had proposed to have right of way along its 220-kV lines. The present crisis emerged after landowners joined together and protested against the new line and sought more compensation. The landowners suggested a route through Kuttanad, which was not acceptable to the authorities.

ADVERTISEMENT

This is a Premium article available exclusively to our subscribers. To read 250+ such premium articles every month
You have exhausted your free article limit.
Please support quality journalism.
You have exhausted your free article limit.
Please support quality journalism.
The Hindu operates by its editorial values to provide you quality journalism.
This is your last free article.

ADVERTISEMENT

ADVERTISEMENT