Power outage as plants trip

Updated - November 17, 2021 05:54 am IST

Published - July 04, 2014 10:32 pm IST - VISAKHAPATNAM:

Due to continuous running of units and coal shortage at thermal power plants, about five units in Andhra Pradesh, including a part of the central grid, tripped, forcing APEPDCL to employ emergency load relief.

The tripped units include VTPS 210 MW, RTPP 210MW, Krishnapatnam 250 MW, NTPC Simhadri 500 MW and NTPC central grid 700 MW.

While the total demand was 2200MW, the scheduled supply was 1546 MW and due to which the power outage in zone four was increased from 2 hours to 4 hours and in zone 2 and 3 from 2 hours to 3.5 hours.

ADVERTISEMENT

This is a Premium article available exclusively to our subscribers. To read 250+ such premium articles every month
You have exhausted your free article limit.
Please support quality journalism.
You have exhausted your free article limit.
Please support quality journalism.
The Hindu operates by its editorial values to provide you quality journalism.
This is your last free article.

ADVERTISEMENT

ADVERTISEMENT