361 infrastructure projects show cost overruns of ₹3.77 lakh crore, says Ministry report

September 22, 2019 10:39 am | Updated 10:40 am IST - New Delhi

The brief reasons for time overruns, as reported by various project implementing agencies, are delays in land acquisition, forest clearance and supply of equipment

Photo for representation.

As many as 361 infrastructure projects, each worth ₹150 crore or more, have shown cost overruns to the tune of over ₹3.77 lakh crore owing to delays and other reasons, a report said.

The Ministry of Statistics and Programme Implementation monitors infrastructure projects worth ₹150 crore and above. Of these 1,623 projects, 361 reported cost overruns and 496 time escalation.

“Total original cost of implementation of the 1,623 projects was ₹19,25,107.47 crore and their anticipated completion cost is likely to be ₹23,02,230.50 crore, which reflects overall cost overruns of ₹3,77,123.03 crore (19.59% of original cost),” the ministry’s latest report for May 2019 said.

ADVERTISEMENT

According to the report, the expenditure incurred on these projects till May 2019 was ₹8,91,512.91 crore, which is 38.72% of the anticipated cost of the projects.

However, it said the number of delayed projects decreases to 399 if delay is calculated on the basis of the latest schedule of completion.

For 684 projects, neither the year of commissioning nor the tentative gestation period has been reported.

ADVERTISEMENT

Out of 496 delayed projects, 166 projects have overall delay in the range of 1 to 12 months, 105 projects 13 to 24 months, 128 projects reflect delay in the range of 25 to 60 months and 97 projects show 61 months and above delay.

The average time overrun in these 496 delayed projects is 36.98 months.

The brief reasons for time overruns, as reported by various project implementing agencies, are delays in land acquisition, forest clearance and supply of equipment.

Besides, there are other reasons like fund constraints, geological surprises, geo-mining conditions, slow progress in civil works, shortage of labour, inadequate mobilisation by the contractor, Maoist problems, court cases, contractual issues, ROU/ROW (right of use/right of way) problems, law and order situation, among others, the report said.

It also observed that project agencies are not reporting revised cost estimates and commissioning schedules for many projects, which suggests that time/cost overrun figures are under-reported.

This is a Premium article available exclusively to our subscribers. To read 250+ such premium articles every month
You have exhausted your free article limit.
Please support quality journalism.
You have exhausted your free article limit.
Please support quality journalism.
The Hindu operates by its editorial values to provide you quality journalism.
This is your last free article.

ADVERTISEMENT

ADVERTISEMENT