Passenger amenities pending at Central Metro Rail station

May 16, 2018 01:17 am | Updated 08:56 am IST - CHENNAI

Rail Safety officials have inspected the Egmore and Central Metro stations .

Work on some passenger amenities needs to be completed at Chennai Central Metro Rail station, said a senior official of Commissioner of Rail Safety (CMRS), after inspecting the station.

The CMRS, whose approval is final and mandatory to start operations, visited the underground stretch from Nehru Park to Chennai Central on Monday and Tuesday.

Speaking to

ADVERTISEMENT

The Hindu , the official said, “They have to complete the construction of entry/exit of Chennai Central Metro Rail station and other passenger amenities like staircases. They have employed a lot of people and told us that they will finish this work in a week.”

ADVERTISEMENT

The CMRS carried out an extensive inspection in Chennai Egmore and Chennai Central Metro Rail stations and looked at all facilities available for passengers, functioning of various systems like tunnel ventilation system and fire fighting system. “The other systems and track between the stations are fine,” he said.

The CMRL plans to open only one entry/exit to the Chennai Central station, the largest underground station in the city, for the first few months as construction is still incomplete.

“Only the entry/exit adjacent to Park Station will be opened,” said an official. This means commuters will have to cross the road or use the subway to reach Metro station. Commuters will have access to all the four entry/exit points in a few months, he added.

ADVERTISEMENT

The Chennai Central Metro Rail station spreads over 70,000 sq.m with two levels — one for trains coming from Nehru Park and the other from Washermanpet. Only the level that will have trains from Nehru Park will be open to public in two weeks. The other level will be available after a year.

On Friday and Saturday, the CMRS officials will inspect another underground stretch — Saidapet to AG-DMS. Expecting the the CMRS approval within a week, the CMRL plans to start operations in both these stretches in two weeks.

This is a Premium article available exclusively to our subscribers. To read 250+ such premium articles every month
You have exhausted your free article limit.
Please support quality journalism.
You have exhausted your free article limit.
Please support quality journalism.
The Hindu operates by its editorial values to provide you quality journalism.
This is your last free article.

ADVERTISEMENT

ADVERTISEMENT