BWSSB to hand over 700 km of road to BBMP for restoration

Published - September 28, 2019 08:05 pm IST

It has deposited ₹100 crore with the civic body

The BWSSB has dug up roads to lay Cauvery water supply pipelines and underground drainage in 110 villages in Mahadevapura, Yelahanka, Bommanahalli, Dasarahalli and Rajarajeshwarinagar zones.

The Bangalore Water Supply and Sewage Board (BWSSB) will soon be handing over around 700 km of roads, which were dug up for laying Cauvery water supply pipelines, to the Bruhat Bengaluru Mahanagara Palike (BBMP) for restoration.

Speaking to The Hindu, Tushar Girinath, Chairman of BWSSB, said, “We have already released around 650 km of roads across five zones for restoration work. We have also deposited ₹100 crore with the BBMP towards restoration of dug-up roads.”

The ambitious project of laying Cauvery water supply pipelines in 110 villages in Mahadevapura, Yelahanka, Bommanahalli, Dasarahalli and Rajarajeshwarinagar zones was expected to be completed by May 2019. However, laying of pipes will take another 10 months and underground drainage work in these areas would be completed by 2022, a senior official of BWSSB said.

ADVERTISEMENT

Chairing a public interaction at Kudlu, which was also attended by BBMP officials, Mr. Girinath said BWSSB engineers would visit the stretches where works have been completed to inspect and monitor the process of getting pipeline connections to houses and other establishments. The engineers, along with other officials of the BWSSB, will also be given the responsibility of keeping middlemen out and preventing overpricing of services by technicians, such as plumbers.

Plumbers to be empanelled

The BWSSB will empanel a large number of plumbers in stretches where the work has been completed. “At many places, people are facing the problem of unavailability of plumbers to get the connections. Keeping this problem in mind, we will empanel plumbers to cater to the demand,” said Mr. Girinath.

ADVERTISEMENT

Around 85% of the work of laying pipelines for water has been completed. “The work got delayed due to the time restrictions by the traffic department. We are permitted to work for only seven hours. However, we will ensure that minimum inconvenience is caused to the public,” he said.

This is a Premium article available exclusively to our subscribers. To read 250+ such premium articles every month
You have exhausted your free article limit.
Please support quality journalism.
You have exhausted your free article limit.
Please support quality journalism.
The Hindu operates by its editorial values to provide you quality journalism.
This is your last free article.

ADVERTISEMENT

ADVERTISEMENT