State looking for a way out of the Polavaram impasse

October 21, 2017 12:52 am | Updated 07:29 am IST - Vijayawada

Option of dividing work under consideration, says Uma

A view of the Polavaram project site.

The Andhra Pradesh government is thinking of ways circumventing the problem it was facing with the prime contractor of the Polavaram project. The government took a decision to terminate its contract with Transstroy and call for fresh tenders and the same was discussed in the Cabinet.

But the State government’s trajectory to remove Transstroy was cut short by none other than Union Minister for Water Resources Nitin Gadkari. In an informal chat with the media in New Delhi, the Union Minister said that the cost of the project would go up by nearly 20 % if the contractor was changed.

Minister for Water Resources Devineni Umamaheswara Rao told

ADVERTISEMENT

The Hindu that Transstroy quoted 14% less at the time of tendering.

ADVERTISEMENT

While it was very unlikely that the new contractor would quote 14% less, it was being expected that the new contractor would quote an additional 5 % keeping in the mind the tight deadlines set by the A.P. government.

“We are looking into the possibility of dividing the work into several parts to get it done as per schedule,” Mr .Umamaheswara Rao said.

ADVERTISEMENT

Engineers for new approach

ADVERTISEMENT

Irrigation engineers however feel that the entire project schedule might fall through if the State government, which was executing it, was not given the required freedom. Some of the most sophisticated excavation and building equipment was being used at the Polavaram dam site. There is no provision in the Standard Schedule of Rates (SSR) by which payments are made by the Central government, they say in support of their argument.

The engineers also say that the Engineering, Procurement and Construction (EPC) contract system is not practical for huge projects such as Polavaram. There was often escalation of cost because of a change in designs.

The designs used for tendering were usually rejected by the Central Water Commission (CWC), the final approving authority. A whole new procedure needs to be developed for large projects, they say.

This is a Premium article available exclusively to our subscribers. To read 250+ such premium articles every month
You have exhausted your free article limit.
Please support quality journalism.
You have exhausted your free article limit.
Please support quality journalism.
The Hindu operates by its editorial values to provide you quality journalism.
This is your last free article.

ADVERTISEMENT

ADVERTISEMENT