DC raps Goschen hospital project coordinators

January 19, 2014 10:58 am | Updated May 13, 2016 10:38 am IST - MANGALORE:

Deputy Commissioner A.B. Ibrahim with LadyGoschen building coordinators in Mangalore onSaturday. Photo: R. Eswarraj

Deputy Commissioner A.B. Ibrahim on Saturday expressed his displeasure over the delay in the construction of the new five-storeyed block of the Government Lady Goschen Hospital.

Reviewing the progress of the work on Saturday, Mr. Ibrahim found the project contractor Krishna Shelters had completed only around 30 per cent of the work in nearly 11 months since assigning the work. Mr. Ibrahim pulled up the two project management agencies – the Delhi-based KNY Projects and Nirmiti Kendra – for lack of coordination in the execution of the work.

The Managing Director of Krishna Shelters Raghavendra K.A. said the construction came to a halt for nearly two months for delay in getting necessary clearances and approvals. Mr. Raghavendra said bills worth Rs. 1.6 crore was to be cleared.

ADVERTISEMENT

This is a Premium article available exclusively to our subscribers. To read 250+ such premium articles every month
You have exhausted your free article limit.
Please support quality journalism.
You have exhausted your free article limit.
Please support quality journalism.
The Hindu operates by its editorial values to provide you quality journalism.
This is your last free article.

ADVERTISEMENT

ADVERTISEMENT