Official apathy irks Ponnuraj

Published - August 13, 2010 03:54 pm IST - MANGALORE:

MANGALORE: An official speaks at a meeting convened by Deputy Commissioner V. Ponnuraj to discuss MP and MLAs' local area development fund schemes in Mangalore on Thursday. PHOTO: CONTRIBUTOR

Deputy Commissioner V. Ponnuraj said on Thursday that 1,675 development projects were lying incomplete in Dakshina Kannada since 2003-04. They were taken up under the local area development schemes of MPs and MLAs, and with the calamity relief fund.

At a meeting to review the progress of various projects at his office here, he said the concerned engineers from the zilla panchayat, Public Works Department and Mangalore City Corporation were responsible for the delay in completing them.

Quality of work in many projects was not up to the mark. Many roadworks had not been taken up according to the guidelines, he said.

ADVERTISEMENT

He said that he would not release payment for such works unless quality was maintained.

“I will have to suspend all of you for not adhering to the norms and the guidelines. But I will not do so now. Instead, I will make payment only to the extent of the works completed,” he said.

Due to the lacunae in the reports and drawbacks in the photographs of the works executed attached with the reports, his office had not cleared some of the bills, he said.

ADVERTISEMENT

Display boards

Mr. Ponnuraj said that a display board mentioning the details of the work should be compulsorily erected at the places of work. But many contractors were not adhering to this rule and the engineers were not insisting on it being followed.

MLA K. Abhayachandra Jain said that this rule was being violated in the district for many years. “Rules have to be strictly followed in every government work,” he said.

The Deputy Commissioner said that a Union Government team, which had visited the district in March (when he was not the Deputy Commissioner of Dakshina Kannada), had sought a report from him on certain violations in the execution of various projects and wanted to know why the engineers were not adhering to the guidelines.

This is a Premium article available exclusively to our subscribers. To read 250+ such premium articles every month
You have exhausted your free article limit.
Please support quality journalism.
You have exhausted your free article limit.
Please support quality journalism.
The Hindu operates by its editorial values to provide you quality journalism.
This is your last free article.

ADVERTISEMENT

ADVERTISEMENT