Sreedharan voices concern over idling men, machinery

January 29, 2014 01:29 pm | Updated May 13, 2016 01:04 pm IST - KOCHI:

‘Disruption of work will hit metro commissioning in 2016’

E. Sreedharan. File Photo: S. Mahinsha

Delhi Metro Rail Corporation (DMRC) Principal Advisor E. Sreedharan has expressed concern over men and machinery idling at Kochi Metro’s casting yard at HMT, Kalamassery, due to the interference of trade unions.

The ‘passive’ approach of the district-level Labour Disputes Redress Committee (headed by the District Collector) to the issue was to be blamed, he told mediapersons here on Tuesday.

Dozens of unskilled people were intruding into the worksite frequently, demanding work and wages, he said. The Kochi Metro’s proposed commissioning in 2016 would suffer if such trends continued, he said after visiting the worksites at Muttom and Edappally.

ADVERTISEMENT

As per schedule, all girders along the Aluva-international stadium stretch had to be launched by January 2015. The rest of the work could be taken up after this. Each day’s delay in commissioning the project would increase the cost by Rs.40 lakh, Mr. Sreedharan said.

This is a Premium article available exclusively to our subscribers. To read 250+ such premium articles every month
You have exhausted your free article limit.
Please support quality journalism.
You have exhausted your free article limit.
Please support quality journalism.
The Hindu operates by its editorial values to provide you quality journalism.
This is your last free article.

ADVERTISEMENT

ADVERTISEMENT