‘Delhi Metro Phase IV tunnelling likely from Nov.’

October 23, 2020 01:38 am | Updated 01:38 am IST - NEW DELHI

Lowering of first boring machine starts

The lowering of the first Tunnel Boring Machine (TBM) in the Phase IV network began at Vikaspuri on the proposed Janakpuri West-R.K. Ashram Marg corridor. As a part of the tunnelling drive, two tunnels, with a length of 1.4 km will be bored between Vikaspuri and Krishna Extension Park, the Delhi Metro Rail Corporation said on Thursday.

“The tunnelling work with the TBM is expected to start next month after the lowering and assembling of the 73 m-long machine is completed. These tunnels will be located between Janakpuri West and Krishna Park Extension stations of the corridor. It will start from Vikaspuri area in continuation of the Magenta Line tunnel that has already been constructed for the currently operational Botanical Garden-Janakpuri West corridor,” DMRC spokesperson Anuj Dayal said.

To take 15 months

ADVERTISEMENT

The tunnel will be constructed approximately at a depth of 14 to 16 metres and the entire tunnelling work on the stretch is expected to be completed in 15 months, the public transporter said. “The alignment of the tunnel will be along the Outer Ring Road. As part of the Phase IV network work approved so far, around 27 km of underground lines will be constructed. The Janakpuri West-R.K. Ashram Marg corridor will have 7.74 km of underground sections,” Mr. Dayal said.

This is a Premium article available exclusively to our subscribers. To read 250+ such premium articles every month
You have exhausted your free article limit.
Please support quality journalism.
You have exhausted your free article limit.
Please support quality journalism.
The Hindu operates by its editorial values to provide you quality journalism.
This is your last free article.

ADVERTISEMENT

ADVERTISEMENT