Cabinet nod for revised Signature Bridge estimate

July 13, 2018 12:00 am | Updated 03:49 am IST - New Delhi

Rs. 1,518.37 cr will be used to complete construction and build an approach road

A view of the under-construction Signature Bridge over the Yamuna river in Wazirabad.

A view of the under-construction Signature Bridge over the Yamuna river in Wazirabad.

The Delhi Cabinet on Thursday approved the final revised estimate for the Signature Bridge in north-east Delhi’s Wazirabad at a meeting chaired by Chief Minister Arvind Kejriwal.

Deposit work

The government statement announcing the development said the Public Work Department’s final revised estimate of Rs. 1,518.37 crore was approved for completion of construction work for the bridge over the Yamuna and the approach road as recommended by the Expenditure Finance Committee (EFC).

In October 2003, the statement said, the Delhi government had decided to outsource the project for which Delhi Tourism and Transportation Development Corporation Limited (DTTDC) submitted its offer to undertake the construction of the bridge at Wazirabad as a deposit work with departmental charges at the rate of 5% of the estimated cost.

The offer was considered favourably and project was entrusted to the DTTDC as a deposit work, with a memorandum of undertaking being signed between the Delhi government, represented by the Secretary, PWD, and the DTTDC, represented by the Chief Engineer, on August 27, 2004.

Third party evaluation

“Since there was difference of opinion between PWD and DTTDC engineers on quantity and justification for escalated cost, it was proposed to get a third party evaluation done. Deputy Chief Minister and Finance Minister Manish Sisodia had decided on March 7 this year that opinion of the Central Public Works Department [CPWD] be obtained and finalised as soon as possible,” the statement said.

The CPWD had examined four major contentious issues and gave its opinion.

These included escalation in the amount which worked out to the tune of Rs. 266 crore as statutory payment to the contractor on account of escalation as per provisions of the agreement.

The issue of lifts was also examined and an additional amount of Rs. 4.80 crore was considered in the revised sanction is in order, the statement said.

Similarly, an additional amount of Rs. 14.90 crore was considered for the pylon access system.

Top News Today

Comments

Comments have to be in English, and in full sentences. They cannot be abusive or personal. Please abide by our community guidelines for posting your comments.

We have migrated to a new commenting platform. If you are already a registered user of The Hindu and logged in, you may continue to engage with our articles. If you do not have an account please register and login to post comments. Users can access their older comments by logging into their accounts on Vuukle.