Vedanta moves Madras High Court seeking permission to maintain its Sterlite copper plant

Firm accuses TNPCB and Thoothukudi district administration of having failed to maintain it.

July 17, 2020 12:22 am | Updated 12:22 am IST - CHENNAI

Vedanta Limited has approached the Madras High Court seeking permission to carry out essential maintenance activities at its Thoothukudi Sterlite copper smelting plant, which remains sealed since May 28, 2018, until the court pronounces its verdict on cases challenging permanent closure of the plant.

In an additional affidavit filed in the court on Thursday, the company alleged that the Tamil Nadu Pollution Control Board (TNPCB) as well as the district administration had failed to maintain the plant and its machinery properly as assured to the court and such indifference had caused grave threat to structural stability of the entire plant.

Referring to a spate of industrial accidents reported across the country in chemical / metallurgical plants due to unexpected shutdown of factories due to the lockdown to fight COVID-19, Vedanta said regular maintenance of such plants was highly essential not only for their upkeep but also to ensure prevention of any environmental hazards.

The company pointed out that it had filed a batch of writ petitions in the High Court last year challenging different orders passed by the State government and the TNPCB refusing renewal of consent to operate the plant, ordering disconnection of power supply and deciding to seal the entire plant and not allow it to be reopened permanently.

Right at the stage of admission of those cases, the company insisted upon interim orders permitting it to maintain the plant. However, it decided to get along with the hearing on the main cases itself since it was assured that the TNPCB as well as the district administration would take care of the maintenance and ensure that there was no environmental hazard.

Though the hearing got completed on January 8 this year and the judgement was reserved, the officials had completely failed to maintain the plant which had suffered severe water logging owing to seasonal rains and overflow of storm water from the rainwater collection sumps. The plant was now inundated posing grave threat to people in the vicinity, it claimed.

Estimating that it would require 750 personnel to undertake the care and maintenance activities, the company said, and urged the court to grant permission only for such activities. It gave an undertaking that it shall not commence regular operations without the express leave of the court if such interim permission to maintain the plant was granted.

0 / 0
Sign in to unlock member-only benefits!
  • Access 10 free stories every month
  • Save stories to read later
  • Access to comment on every story
  • Sign-up/manage your newsletter subscriptions with a single click
  • Get notified by email for early access to discounts & offers on our products
Sign in

Comments

Comments have to be in English, and in full sentences. They cannot be abusive or personal. Please abide by our community guidelines for posting your comments.

We have migrated to a new commenting platform. If you are already a registered user of The Hindu and logged in, you may continue to engage with our articles. If you do not have an account please register and login to post comments. Users can access their older comments by logging into their accounts on Vuukle.