Supreme Court refuses to restrain coal companies from mining operations

Coal companies have six-months time to wind up their operations, the apex court said

October 16, 2014 12:22 pm | Updated November 17, 2021 04:57 am IST - New Delhi

KHAMMAM_(ANDHRA PRADESH)_ A view of Coal production at an open cast mine at Yellandu in Khammam District on Monday. PHOTO_G_N_RAO  - KHAMMAM_(ANDHRA PRADESH)_ A view of Coal production at an open cast mine at Yellandu in Khammam District on Monday. PHOTO_G_N_RAO

KHAMMAM_(ANDHRA PRADESH)_ A view of Coal production at an open cast mine at Yellandu in Khammam District on Monday. PHOTO_G_N_RAO - KHAMMAM_(ANDHRA PRADESH)_ A view of Coal production at an open cast mine at Yellandu in Khammam District on Monday. PHOTO_G_N_RAO

The Supreme Court on Thursday refused to restrain coal companies, which were directed to wind up mining operations in six months after their coal block allocations were cancelled by it, from extracting coal during this period and selling it in the market.

A bench headed by Chief Justice H.L. Dattu said, the apex court had granted six months’ time to wind up their operations and the companies cannot be restrained from excavating coal during this period.

“If they want to excavate coal, no one can stop them. They have been given six months’ time. Why should court direct them not to extract coal during this period,” the bench said.

The court’s observation came when advocate M.L. Sharma, on whose plea the apex court had earlier cancelled 214 out of 218 coal blocks allocation, submitted that the companies are extracting three to four times more coal per day as they have to wind up the operations within six months.

He submitted that the companies should be restrained from doing so, but the apex court refused to entertain his plea.

On September 24, the apex court had quashed the allocation of 214 coal blocks allocated since 1993, terming it as “fatally flawed” and had allowed the Centre to take over operation of 42 such blocks which are functional.

It had asked Coal India Limited (CIL) to fill the void and take over the operation of the 42 functional blocks, saying that the cancellation of these blocks will take effect only after six months from March 31, 2015.

The apex court had given the time after it was submitted by the Attorney General that the Centre and CIL need some time to adjust to the changed situation and move forward.

Top News Today

Sign in to unlock member-only benefits!
  • Access 10 free stories every month
  • Save stories to read later
  • Access to comment on every story
  • Sign-up/manage your newsletter subscriptions with a single click
  • Get notified by email for early access to discounts & offers on our products
Sign in

Comments

Comments have to be in English, and in full sentences. They cannot be abusive or personal. Please abide by our community guidelines for posting your comments.

We have migrated to a new commenting platform. If you are already a registered user of The Hindu and logged in, you may continue to engage with our articles. If you do not have an account please register and login to post comments. Users can access their older comments by logging into their accounts on Vuukle.