Vizhinjam port | Adani Group gets environmental nod for five more quarries

Adani Group had approached Kerala government seeking permission to operate 16 quarries

July 19, 2022 09:29 pm | Updated July 20, 2022 09:21 am IST - THIRUVANANTHAPURAM

A view of an abandoned granite quarry near Kovalam in Thiruvananthapuram. File

A view of an abandoned granite quarry near Kovalam in Thiruvananthapuram. File | Photo Credit: GOPAKUMAR S.

The Adani group has received environmental clearance to open 10 new quarries so far in Thiruvananthapuram, Kollam, and Pathanamthitta districts.

The group had approached the government seeking permission to operate 16 quarries, eight under direct control and the rest with private partnership on the condition of providing 50% of stock in each quarry for Vizhinjam port works.

For breakwater construction

The State had issued licence to operate five quarries so far, of which two are under the direct control of Adani. Environmental clearance for five quarries has been granted now, which will be functional soon, and three are under the process of getting clearance. Similarly, three applications are also under the consideration of various departments.

Speaking to The Hindu, an official said the process of granting licences for new quarries had many formalities. The Revenue department had provided no-objection certificate to all the 16 quarries. But it would take over an year to get all clearances.

Boulder shortage

Adani Vizhinjam Port Private Limited (AVPPL), entrusted to develop and operate the deep-water multipurpose port, had approached the government seeking permission for quarrying inside the State in the wake of shortage of boulders for construction of the 3.1 km-long breakwater as part of port construction.

The port developer could procure only 40.23 lakh tonne of granite so far, around 46% of the estimated 87 lakh tonne required for construction.

Officials said there was no other way other than granting licence for quarrying in the State to complete the work at least by next year. Though the Port department had set a deadline for completing the work by May 2023 to bring a ship to the port, it remained to be seen whether the work could be finished by the deadline.

0 / 0
Sign in to unlock member-only benefits!
  • Access 10 free stories every month
  • Save stories to read later
  • Access to comment on every story
  • Sign-up/manage your newsletter subscriptions with a single click
  • Get notified by email for early access to discounts & offers on our products
Sign in

Comments

Comments have to be in English, and in full sentences. They cannot be abusive or personal. Please abide by our community guidelines for posting your comments.

We have migrated to a new commenting platform. If you are already a registered user of The Hindu and logged in, you may continue to engage with our articles. If you do not have an account please register and login to post comments. Users can access their older comments by logging into their accounts on Vuukle.