An 800 MW power station can be established at Idukki, says pre-feasibility study

Taking the combined installed capacity of the Idukki hydroelectric power project to 1580 MW, the scheme is designed to address the long-term power demands of the State

November 29, 2021 01:13 pm | Updated 01:13 pm IST - THIRUVANANTHAPURAM:

File photo. Kulamavu Dam, one of the three dams of Idikki Hydel Project

File photo. Kulamavu Dam, one of the three dams of Idikki Hydel Project

An 800 MW power station can be established at Idukki to complement the existing 780 MW power gneration facility, a pre-feasibility study prepared by WAPCOS has indicated. Taking the combined installed capacity of the Idukki hydroelectric power project to 1580 MW, the scheme is designed to address the long-term power demands of the State.

State power utility Kerala State Electricity Board (KSEB) hopes to begin work on the 'Idukki Golden Jubilee Extension Scheme,' estimated to cost ₹2699.67 crore, in 2023 and complete it within five years.

The Minister for Electricity, K. Krishnankutty, released the pre-feasibility report prepared by central government agency WAPCOS here on November 29. This scheme, along with the Soura rooftop solar plant initiative, will is a critical component in addressing the power requirements of the state for the next 30 years, KSEB chairman and managing director B. Ashok said.

Planned at Moolamattam 500 metres north of the existing underground station, the proposed power station will draw water from the Idukki reservoir. The intake structure is planned on the left bank of the Kulamavu dam. A new penstock pipe will be laid from the reservoir for carrying water to the station, which too is planned as an underground facility. The tailrace water will be released into the Thodupuzha river in the Muvattupuzha basin.

The station will be equipped with four generators having a capacity of 200 MW each as opposed to six at the existing station. In due course, the old station, which was commissioned in 1976, will be kept as a standby, KSEB officials said.

The extension scheme has been necessitated by the fact that the evening peak demand (6.30 p.m. to 10.30 p.m.) in the state has risen to 3966 MW and morning peak to 3200 MW.

As per the pre-feasibility report, the civil works are estimated to cost ₹1309.67 crore and electromechanical works, ₹1360 crore.

The KSEB needs to obtain nine crucial clearances before it can move forward with the project. It expects to apply for clearance from the Ministry of Environment and Forests in January 2022. The detailed project report and environment impact assessment report are expected in September 2022. The bid documents will be ready by November 2022. Environment clearance is expected, at the earliest, by March 2023.

0 / 0
Sign in to unlock member-only benefits!
  • Access 10 free stories every month
  • Save stories to read later
  • Access to comment on every story
  • Sign-up/manage your newsletter subscriptions with a single click
  • Get notified by email for early access to discounts & offers on our products
Sign in

Comments

Comments have to be in English, and in full sentences. They cannot be abusive or personal. Please abide by our community guidelines for posting your comments.

We have migrated to a new commenting platform. If you are already a registered user of The Hindu and logged in, you may continue to engage with our articles. If you do not have an account please register and login to post comments. Users can access their older comments by logging into their accounts on Vuukle.