Kottur-Harihar rail line yet to be opened

December 26, 2013 02:11 am | Updated 02:11 am IST - BANGALORE:

The 67-km Kottur-Harihar new railway line, though was completed three years ago, is yet to see operation of trains as a ginger group of farmers in and around Ganganarsi village in Harihar taluk are obstructing the South Western Railway from giving the final touches to the completed track.

The farmers owing land between the 25-km stretch of Harapanahalli and Amaravati Junction (about 5 km from Harihar) have been demanding higher compensation for their 250 acres of land acquired for the project. Though the foundation stone was laid for the railway line in 1995 by the then Railway Minister C.K. Jaffer Sharief, the acquisition process commenced in 2002, sources told The Hindu .

Those demanding higher compensation approached court and 495 cases were filed. Of these, over 400 have been disposed of directing higher compensation to farmers.

The South Western Railway has deposited Rs. 1.21 crore with the district administration for payment of enhanced compensation. Still, a group of farmers has been obstructing work demanding Rs. 7 lakh an acre compensation, the sources said.

Davangere South MLA S.S. Mallikarjun, in whose constituency Amaravati Junction and Goods Shed fall, said that he is trying to convince the farmers to allow the Railways to open the line.

It is in the interests of the district and the region that the line should become operational, Mr. Mallikarjun said.

The South Western Railway authorities too wrote to the Chief Secretary on December 19 highlighting their plight and urging the State government to convince the farmers that the line be opened.

Reduction in distance

K.N. Krishnaprasad, who keenly follows developments in the railway sector, pointed out that the new line provided the shortest rail route between Chennai and Mangalore.

The distance between Hospet and Chikjajur Junction will reduce at least by 50 km from the regular routes — via Rayadurg and Chitradurga or Hubli and Haveri. Due to the inordinate delay in completing the project, the cost has shot up from Rs. 65 crore to Rs. 439 crore.

Railway Minister M. Mallikarjun Kharge was, however, hopeful of the State government resolving the farmers’ issue amicably. He said that once the issue is settled, the South Western Railway could complete the remaining work within a couple of months.

0 / 0
Sign in to unlock member-only benefits!
  • Access 10 free stories every month
  • Save stories to read later
  • Access to comment on every story
  • Sign-up/manage your newsletter subscriptions with a single click
  • Get notified by email for early access to discounts & offers on our products
Sign in

Comments

Comments have to be in English, and in full sentences. They cannot be abusive or personal. Please abide by our community guidelines for posting your comments.

We have migrated to a new commenting platform. If you are already a registered user of The Hindu and logged in, you may continue to engage with our articles. If you do not have an account please register and login to post comments. Users can access their older comments by logging into their accounts on Vuukle.