Escoms suffered losses due to delayed works, award of contract to ineligible firms: CAG

Incurred an additional expenditure of ₹225.49 crore owing to delay in execution of works

September 20, 2022 07:02 pm | Updated September 21, 2022 01:26 pm IST - Bengaluru

The CAG report for the year 2022, which was tabled in the Karnataka Legislative Assembly on Tuesday, noted that there was compromise in the quality of material used in electrical works.

The CAG report for the year 2022, which was tabled in the Karnataka Legislative Assembly on Tuesday, noted that there was compromise in the quality of material used in electrical works. | Photo Credit: MURALI KUMAR K

Electricity Supply Companies (Escoms) in Karnataka delayed by 12 to 37 months completion of various works under the Deendayal Upadhyaya Gram Jyoti Yojana (DDUGJY) and awarded contracts to ineligible firms violating the prevailing rules, said The Comptroller and Auditor General (CAG) of India.

Quality compromised

The CAG report “DDUGJY/Pradhan Mantri Sahaj Bilji Har Ghar Yojana” for the year 2022, which was tabled in the Legislative Assembly on Tuesday, noted that there was compromise in the quality of material used in electrical works.

Escoms had incurred an additional expenditure of ₹225.49 crore owing to delay in the execution of works. Delay in availability of lands and in availing clearances from forest and railways caused breach of timelines for completion of work and deferring the envisaged benefits to the beneficiaries, it said.

Escoms incurred additional expenditure of ₹26.42 crore on project management consultants due to fixation of higher fees than that stipulated under the scheme. Escoms incurred extra expenditure of ₹39.67 crore on procurement of material at higher rates over and above the Central procurement prices, the CAG said.

Contracts extended

The report said the contracts were extended without levying a penalty of ₹3 crore on the defaulting contractors in violation of the general conditions of contracts/terms of detailed work award, defeating the purpose of inclusion of penal clause in the contract to act as deterrent on non-performing contractors.

Although Escoms achieved targets under the scheme, there were cost and time overruns due to deficiencies in planning and implementation whereby the envisaged benefits had either been deferred or not been achieved in true terms, the report said.

0 / 0
Sign in to unlock member-only benefits!
  • Access 10 free stories every month
  • Save stories to read later
  • Access to comment on every story
  • Sign-up/manage your newsletter subscriptions with a single click
  • Get notified by email for early access to discounts & offers on our products
Sign in

Comments

Comments have to be in English, and in full sentences. They cannot be abusive or personal. Please abide by our community guidelines for posting your comments.

We have migrated to a new commenting platform. If you are already a registered user of The Hindu and logged in, you may continue to engage with our articles. If you do not have an account please register and login to post comments. Users can access their older comments by logging into their accounts on Vuukle.