Completion of new 800-MW unit at NTTPS likely to take another four to six months 

April 15, 2022 08:12 pm | Updated 08:12 pm IST - VIJAYAWADA

The Dr. Narla Tatarao Thermal Power Station near Vijayawada on Friday.  
Photo: K.V.S. Giri/ THE HINDU

The Dr. Narla Tatarao Thermal Power Station near Vijayawada on Friday. Photo: K.V.S. Giri/ THE HINDU | Photo Credit: KVS GIRI

The AP-Genco’s new 800-MW unit at Dr. Narla Tatarao Thermal Power Station (NTTPS) at Ibrahimpatnam, near here, is likely to be ready for commissioning in another four to six months provided the contractor — BGR Energy Systems (BES) — carries out the balance-of-plant works on a war-footing. 

The BES began BoP works way back in 2017-18, but it could not stick to the timelines due to its financial woes, labour issues and some extraneous factors including the COVID pandemic. 

The Andhra Pradesh government tried its best to get the BoP component finished as per schedule, but gave a few extensions of time, which resulted in the overall project being delayed inordinately. 

According to reliable sources, the BoP works are at this moment not going on at the desired pace, but are set to  gather steam in the coming days  due to mounting pressure from the government which requires incremental capacity additions as the mismatch between demand and supply continues especially during the summer, and is barely able to overcome the nagging coal crisis. 

The public sector behemoth BHEL had been entrusted with the task of installing the Boiler-Turbine-Generator (BTG) part. 

Now, the sticking point in the whole project is that both the BTW and BoP works ought to be executed simultaneously, but the delay is apparently on the part of BES, which has to construct coal bunkers and conveyor belts and finish other works. 

Only then BHEL can install the BTG and the commercial operations date can be fixed. While this is so, BES might pitch for sanction of escalation of costs. 

The existing capacity of NTTPS is 1,760 Megawatts comprising six units of 210 MW each and a single unit of 500 MW capacity. 

NTTPS is one of the three major thermal power plants in Andhra Pradesh, the others being the 1,600-MW Sri Damodaram Sanjeevaiah Thermal Power Station at Krishnapatnam (a new 800-MW unit is almost ready for commissioning here) and the 1,650-MW Rayalaseema Thermal Power Plant in Kadapa district. 

0 / 0
Sign in to unlock member-only benefits!
  • Access 10 free stories every month
  • Save stories to read later
  • Access to comment on every story
  • Sign-up/manage your newsletter subscriptions with a single click
  • Get notified by email for early access to discounts & offers on our products
Sign in

Comments

Comments have to be in English, and in full sentences. They cannot be abusive or personal. Please abide by our community guidelines for posting your comments.

We have migrated to a new commenting platform. If you are already a registered user of The Hindu and logged in, you may continue to engage with our articles. If you do not have an account please register and login to post comments. Users can access their older comments by logging into their accounts on Vuukle.